Date
Attendees
Goals
- Set and status planning activities for detector development and deployment.
Discussion items
Time | Item | Who | Notes |
---|
30 min | Deployment 3-wk plan | KP | Plans to support upcoming experiments. - JF Commissioning (week of Aug 1?): Commissioning test plan in draft form.
- ePix10k2M.1 to MFX (by week of July 13, pending Silke)
- Collect and analyze any remaining in-lab test data.
- Solid pedestals
- Noise map
- Response uniformity (mini-X)
- Bootstrap gain (sealed source)
- Linearity (signal injection)
- Document results in 'traveller' on confluence
- ePix10k2M.0 to XCS(?) (by week of July 20)
- Next detector deployed: Kayla to lead meeting for mapping detectors to experiments.
|
30 min | Status | All | - Group priorities review:
- Detectors for Run 18
- Jungfrau commissioning plan and commissioning tests (Comments on plan? Determine flux))
- ePix10k2M (new) Final tests before deployment, commissioning test plan commissioning/calibration along same lines as JF.
- ePix10k2M (old) Needs shroud re-replaced, plans for backplate replacement.
- ePix smalls tests to match.
- Meet w/Mason re chiller troubleshooting Wed. 1pm
- Detectors under development
- RIXS-CCD, review draft Project Plan w/NEH 2.2
- RIXS-CCD Concept Design (R to set meeting to talk cooling options)
- Anton project at UCB/SSL (milestone/schedule revision received)
- SXR Downselect prep
- Lab 'commissioning'
- DAQ
- Storage nodes
- LCLS I/II compatibility
- Table seismic
- Laser table re-cert
- BIO for racks in chase
- DP node purchase
- Sealed source purchase (M&S evaporating)
Actions: - check with TID about status of small epix100/10ka. (Mark, query sent)
- check what cables we need for the in-vac epix100 setup in MEC and CXI. (Philip)
- Leak check Kimball rig (1e-8 on Thu, probably good for next steps)
- Laser recertification (Kaz)
- Wave8-V2 tests (Kaz)
- RIXS system pumpdown and noise vs. temp (3e-7 on Thur, ready for next steps)
Other news: - ePix10k2M calibration/communication progress continues, escalation necessary?
|
5 min | Budget Update | mmck |
- Labor snapshot (May. actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business | | |
Action items