Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minDeployment 3-wk planTeam

Plans to support upcoming experiments.

  • JF Commissioning (week of Aug 1?): Commissioning test plan in draft form.
  • ePix10k2M.1 to MFX (by week of July 13, pending Silke)
    • Collect and analyze any remaining in-lab test data.
      • Solid pedestals
      • Noise map
      • Response uniformity (mini-X)
      • Bootstrap gain (sealed source)
      • Linearity (signal injection)
      • Document results in 'traveller' on confluence
  • ePix10k2M.0 to XCS(?) (by week of July 20)
    • Same test data as for .1
  • Next detector deployed: Kayla to lead meeting for mapping detectors to experiments.
30 minStatusAll
  • Group priorities review:
    • Detectors for Run 18
      • Jungfrau commissioning plan and commissioning tests (Comments on plan? Determine flux))
      • ePix10k2M (new) Final tests before deployment, commissioning test plan commissioning/calibration along same lines as JF.
      • ePix10k2M (old) Needs shroud re-replaced, plans for backplate replacement.
      • ePix smalls tests to match.
      • Meet w/Mason re chiller troubleshooting Wed. 1pm

    • Detectors under development
      • RIXS-CCD, review draft Project Plan w/NEH 2.2
      • RIXS-CCD Concept Design (R to set meeting to talk cooling options)
      • Anton project at UCB/SSL (milestone/schedule revision received)
      • SXR Downselect prep

    • Lab 'commissioning'
      • DAQ
        • Storage nodes
        • LCLS I/II compatibility
      • Table seismic
      • Laser table re-cert
      • BIO for racks in chase
      • DP node purchase
      • Sealed source purchase (M&S evaporating)


Actions:

    • check with TID about status of small epix100/10ka. (Mark, query sent)
    • check what cables we need for the in-vac epix100 setup in MEC and CXI. (Philip)
    • Leak check Kimball rig (1e-8 on Thu, probably good for next steps)
    • Laser recertification (Kaz)
    • Wave8-V2 tests (Kaz)
    • RIXS system pumpdown and noise vs. temp (3e-7 on Thur, ready for next steps)
    • Philip may be hearing from ALS regarding JF, PD may want to make use of PQ laser.



Other news:

ePix10k2M calibration/communication progress continues, escalation necessary?

CH: USB patch cord available??

  • Fluorescence calculations to help with??

 

RA: Beam pipes for 2M? No.

  • Loan stages to CXI....ensure return.
  • Meet re cooling concepts...met with Jim re outside space: not much.

 

KP: JSA summary list circulated

  • Small Rayonix to be tested in XPP...manual available??

 

 

 

5 minBudget Updatemmck
  • M&S Status (Through May)



  • Labor snapshot (May. actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items