Date
Attendees
Goals
- Set and status planning activities for detector development and deployment.
Discussion items
Time | Item | Who | Notes |
---|
30 min | Deployment 2-wk plan | KP | Plans to support upcoming experiments (in-work, Kayla has scheduled meeting for Thursday) |
30 min | Status | All | - Group priorities review:
- Detectors for Run 18
- Jungfrau commissioning plan and commissioning tests (Comments on plan? Actions from meeting with Meng to select targets, determine flux))
- ePix10k2M (new) Final tests before deployment, commissioning test plan commissioning/calibration along same lines as JF.
- ePix10k2M (old) metrology, done, collect from TID, deploy mid-July.
- ePix smalls tests to match
- Detectors under development
- RIXS-CCD, review draft Project Plan w/NEH 2.2
- RIXS-CCD Concept Design (meeting with Lin 3pm today to discuss vibe characterization)
- Anton project at UCB/SSL (milestone/schedule revision received)
- SXR Downselect prep
- Lab 'commissioning'
- Kimball leak test this week (general purpose JSA status?)
- DAQ
- Storage nodes
- LCLS I/II compatibility
- Table seismic
- Laser table re-cert
Actions: - check with TID about status of small epix100/10ka. (Mark, query sent)
- check what cables we need for the in-vac epix100 setup in MEC and CXI. (Philip)
- Leak check Kimball rig, and do vacuum test over several days (Conny/Rebecca)
- Laser recertification (Kaz)
- Wave8-V2 tests (Kaz)
- RIXS system pumpdown and noise vs. temp (Conny/Rebecca)
Other news: - Data management meeting (pt. 2) July 2
- ePix Quads FDR completed, passed.
- ICD review with NEH 2.2 2:30pm today.
- Framing Camera whitepaper acknowledged by Kramer, no review yet.
- ePix10k2M calibration/communication progress continues, no escalation presently necessary.
- Priorities:
- JF commissioning tests.
- ePix10k setup, calibration.
- RIXS-CCD project plan/concept design
- Calibrations/procedure developments for detector deployments, starting with ePix.
- Wave8 readiness.
- BIO for racks in chase.
- Seismic table mount components received
|
5 min | Budget Update | mmck |
- Labor snapshot (May. actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business | | |
Action items
- Action: Kazutaka Nakahara to circulate and/or post chiller manual to confluence.
- Action: Kazutaka Nakahara to run chiller over weekend to check stability, IOC performance.
- Action: Zimmerman, Kayla to provide update on the e-gun/RP JSA approval status.
- Action: Rebecca to rough out Concept Design for June 26 review.