List of things to do:
- Start QNAP NAS (in S20 gallery) and ask Ken/Jeremy to mount it on all facet computers (facet-srv20, cpu-liXX-pmXX)
- Test DAQ
- Check pico motor servers are running
- Check state of flippers. They might have gone to an unsafe state.
- Home UPX stages. Do this only for stages you know are safe to move.
- Test transmission through IP with alignment laser. The oven mover, actuators with foils or wire scanners may be in an undefined state.
Things to check: | 3/2/24 outage | System owner: | Notes: |
---|---|---|---|
Oven mover is in bypass position | Doug S. | Required to clear MPS fault. | |
Retract the DS Be window | Doug S. / Ivan | ||
PB, spectrometer, and laser transport turbos on | Doug S. / Ivan | ||
When LCW is off: Ensure beamline valves inserted, DPS turbos and roughing pumps are OFF. | Doug S. | ||
When LCW is back on: DPS pumps restarted (US and DS turbos and roughing pumps).
| Ops / Doug S. | DS Be window should be retracted first | |
DPS Vacuum watcher restarted | Ops / Doug S. | ||
Spectrometer Camera Checkout Procedure | Doug S. | ||