Below is a list of beamtimes and what is intended to be evaluated during those beamtimes:

Table 1. Beamtimes and what is intended to be evaluated.

Camera testing

Station

Dates

Objective

ePix10ka small, 2M and NG prototype

MFX

15 July + July 16 (backup shift)

Verify we understand the checker mark problem with the ePix10k small and 2M. Run the Non Ghosting camera and get initial performance data.

ePix10k smalls

MFX

July 21

Retake the calibration data needed to come up with calibration constant for these cameras.

ePixHR

MFX

Aug 29, Sept 14+15

Evaluate the operation and performance of the ePixHR detector (ideally ASIC v4)


Detailed plans and list of measurements performed during the beamtime can be seen by following the links below:

MFX beamtime 15,16, and 21 July