Below is a list of beamtimes and what is intended to be evaluated during those beamtimes:
Table 1. Beamtimes and what is intended to be evaluated.
Camera testing | Station | Dates | Objective |
ePix10ka small, 2M and NG prototype | MFX | 15 July + July 16 (backup shift) | Verify we understand the checker mark problem with the ePix10k small and 2M. Run the Non Ghosting camera and get initial performance data. |
ePix10k smalls | MFX | July 21 | Retake the calibration data needed to come up with calibration constant for these cameras. |
ePixHR | MFX | Aug 29, Sept 14+15 | Evaluate the operation and performance of the ePixHR detector (ideally ASIC v4) |