This is the place where Detector Ops group will keep the most up to date schedule that they have for when detectors prototypes will be delivered to the ASC for integration into the DAQ and initial testing. Currently this contain the timeline for the ePixHR (5kHz), ePixM (5kHz), and the ePixUHR (33kHz) cameras .


ePixHR (5 kHz) camera

For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.

Camera

type

Aim

Date at ASC

ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ and initial testing to feed into ASIC v3. submission.

April 2022

ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ (new firmware structure) and initial testing.

October 2022

ePixHR5kHz

ASIC v3.

Integration into DAQ and initial testing of ASIC.

November 2022

ePixHR5kHz Quad

ASIC v3.

Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ).

December 2022

ePixHR5kHz

full Camera

ASIC v4.

Initial testing of full camera and in lab calibrations.

May 2023


ePixM camera (5 kHz)

A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023.

Camera

type

Aim

Date at ASC

ePixM5kHz

Not back thinned

Integration into DAQ

Feb 2023

ePixM5kHz

Back thinned

Initial testing of the ePixM camera at ASC and in lab calibrations.

March 2023


ePixUHR (33 kHz)

For the UHR camera, the use of a hardware emulator will allow for start of DAQ integration. The first prototype detector will be delivered in April 2023. Commissioning of science cameras will happen in the 2026-2027 time frame.

Camera

type

Aim

Date at ASC

ePixUHR33kHz

HW emulator

Integration into DAQ.

Jan 2023

ePixUHR33kHz


Integration into DAQ and initial testing.

April 2023