This is the place where Detector Ops group will keep the most up to date schedule that they have for when detectors prototypes will be delivered to the ASC for integration into the DAQ and initial testing. Currently this contain the timeline for the ePixHR (5kHz), ePixM (5kHz), and the ePixUHR (33kHz) cameras . Additionally this page will also contain expected delivery dates for production detectors (spares of existing detector types), delivery dates for detectors that is out for refurb, key delivery dates for testing capability, and scheduled beam times.

Prototype Delivery

ePixHR (5 kHz) camera

For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.

Camera

type

Aim

Date at ASC

Previous delivery dateComments

ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ and initial testing to feed into ASIC v3. submission.

April 2022



ePixHR5kHz

ASIC v2.

Integration into the LCLS-II DAQ (new firmware structure) and initial testing.

October 2022



ePixHR5kHz

ASIC v3.

Integration into DAQ and initial testing of ASIC.

November 2022


No longer apply due to v4 ASIC need.

ePixHR5kHz Quad

boards only

Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ).

August 2023

May 2023; end March 2023.; Feb 2023;December 2022This delivery time is for boards only.
ePixHR5kHz small prototypeASIC V4.Small prototype camera for first testing of ASIC v4.August 2023 (camera with sensors)July 2023 (just ASIC, check with kenney about sensor version), June 2023 (pending ASIC submission)

ePixHR5kHz

full Camera

ASIC v4.

Initial testing of full camera and in lab calibrations.


End of November 2023


ePixM camera (5 kHz)

A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023. 3 Cameras will be delivered.

Camera

type

Aim

Date at ASC

Previous delivery date

ePixM5kHz

Not back thinned

Integration into DAQ; Initial ASC performance testing.

End of August

July; Mid May; end March 2023; Feb 2023

ePixM5kHz

Back thinned

Initial testing of the ePixM camera at ASC and in lab calibrations.

December 2023

September 2023; March 2023


ePixUHR (33 kHz)

For the UHR camera, the use of a hardware emulator will allow for start of DAQ integration. The first prototype detector will be delivered in April 2023. Commissioning of science cameras will happen in the 2026-2027 time frame.

Camera

type

Aim

Date at ASC

Previous delivery date

ePixUHR33kHz

HW emulator

Integration into DAQ.

end Feb.

Jan 2023

ePixUHR33kHz


Integration into DAQ and initial testing.

April 2023


Production Camera Delivery

Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

ePix10k small, 1mm Si 

sidefacer

Added to operations; Commissioned by Sebastien.

delivered.

July 2022N/A

ePix10k2M.2

non-ghosting ASICs

Added to operation; currently aimed at MFX but needs to be discussed with beamlines ones it is delivered.

TBD

May 2023; April 2023; Nov. 2022ASAP
ePixM5kHz90To be installed at REXS chamber at qRIXS

April 2023
ePixM5kHz0To be installed at ChemRixs chamber

April 2023
ePixM5kHz?To be installed at the end of new (currently not excisting) spectrometer arm next to qRIXS spectrometer arm

At least a year after first ePixM detector
ePixHR5kHz 2MLarge ePixHR5kHz cameraTo be installed at TXI.

After start 2024 (chamber delivered start 2024)
ePixHR5kHz smallSmall ePixHR5kHz camera; same form factor as side facing ePix100To be installed at TXI.

end of 2023.
ePixHR5kHz smallSmall ePixHR5kHz camera; same form factor as side facing ePix100To be installed at TXI.

end of 2023.
RIXSccdCCDSystem 1, at STA for shimming down the sides and the bolts.Mid AugustJuly 2023October 2023
RIXSccdCCDSystem 2, at STA for shimming down the sides and the bolts.Sept. 2023 (3 weeks after system 1)August 2023 TBD
ePix100 front (1) and sidefacing (2)
OIP
September 2024

Refurb. Delivery

Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

CSPAD 2M

CXI's large CSPAD detector

inner module is broken and need to be replaced. The Detector has been delivered to Kenney together with 2 small CSPAD units to be scavenged for the repair. To be returned for operation at CXI.

Dec 2022

Delivered ASC 2/23/2023

Feb 2023March 2023

Testing capability schedule

Capability

Type

Aim

Date available

Previous availability date

Running LCLS-II detectors at XPP.

LCLS beam line testing

Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there

Available

N/A

Running LCLS-II detectors at MFX.

LCLS beam line testing

Run fiber from RIXS to MFX so LCLS-II detectors (ePixM, ePixHR) can be tested there

Available

N/A

Running LCLS-II detectors at FEH.

LCLS beam line testing

Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI

Available

N/A
E-gun X-ray sourceASC X-ray sourcepulsed X-ray source at ASCTBD
Running ePixM at MFX (Frankenstein)LCLS beam line testinginstall sufficient number of fibers to MFX to run the ePixM cameraJanuaryN/A


DAQ integration estimates:

Capability

Type

Date available estimate

Previous availability dateNote

ePixM

DAQ integration

Jan-Feb 2024

N/ATentative

ePixUHR

DAQ integration

Autumn 2024 (Sept, Oct)

N/Avery tentative

RIXSccd

DAQ integration




JF15M

DAQ integration




TMO Tixel

DAQ integration





DAQ integration





Beamtime schedule

Experiment number

Station

Aim

Dates

Lead from Ops team side

X-10025

MECEnergy and burst rate frontier using a GaAs Icarus Detector.2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day)Philip Hart

DET

MFXEvaluate the checker mark problem on small ePix10k, and the issue with the 3 bad quads for the MFX 2m.2023: July 13 (Night), July 15 (Night)Conny Hansson

X-10051

MFXCalibration of small10k's after having corrected for the checker mark effect.2023: July 21 (Night)Conny Hansson

ePixHR

MFXEvaluate the performance of the ePixHR detector.2023: 14+15 Sept. (night); 23Oct.Conny Hansson

ePixM

MFXEvaluate the performance of the ePixM detector.Early 2024Conny Hansson

ePixM

MFXEvaluate the performance of the ePixM detector.March-April 2024Conny Hansson

ePixM

chemRIXSEvaluate the performance of the ePixM detector.Before June 2024Conny Hansson

RUN 22 (Jan 8 - July 3, 2024)

X-10059

MFXePixHR. Register tunning and performance testing with new settings.Feb 16+17, nightConny Hansson

X-10059

MFXePixHR. 15-Mar, nightConny Hansson

X-10059

MFXePixM15+16-Apr, nightConny Hansson

X-10059

MFXWe canceled it22-Apr, nightConny Hansson

X-10059

MFXePixM12-May, night

Conny Hansson

Potential parasitic time at MFX



TBD

MFXTBD15-17 April, night


TBD

MFXTBD18-19 April, night


TBD

MFXTBD22-Apr, night

TBD

MFXTBD10-14 May, day

TBD

MFXTBD13-14 May, night

TBD

MFXTBD13-15 June, night