Goals
- Set and status planning activities for detector development and deployment.
Discussion items
Time | Item | Who | Notes |
---|
30 min | Deployment 2-wk plan | KP | Plans to support upcoming experiments |
30 min | Status | All | - Group priorities review:
- Detectors for Run 18
- Jungfrau commissioning plan and commissioning tests (meet with Schlotter)
- ePix10k2M (new) commissioning/calibration along same lines as JF
- ePix10k2M (old) metrology and test to match
- ePix smalls tests to match
- Detectors under development
- RIXS-CCD Project Plan
- RIXS-CCD Concept Design
- Anton project at UBD/SSL
- SXR Downselect prep
- Lab 'commissioning'
- Marietta certification
- Mini-X certification
- Kimball certification
- DAQ
- Storage nodes
- LCLS I/II compatibility
- Table seismic
- Laser table re-cert
- B84/B33 JSAs somewhere in TID approval cycle.
- ePix Quads FDR Thursday 4pm, website live.
- ICD review with NEH 2.2 1pm today.
- Framing Camera whitepaper submitted to FES yesterday.
- Stress-test test of JF @CXI.
- ePix10k2M calibration/communication status. Escalate?
- Jungfrau 4M calibration/commissioning plan.
- Priorities:
- JF Stress test.
- ePix10k setup, calibration.
- Calibrations/procedure developments for detector deployments, starting with ePix.
- Wave8 readiness.
- BIO for racks in chase.
- Seismic table mount components received.
- RA: Interns start tomorrow
- PH: ePix/JF analysis database issues...broke LCLS-I analysis
- Calibration discussions w/ CH.
- ePix10k need mtg w/JT
- KN:
- Chiller ran through weekend no issues.
- Want to try solution on other failed chiller
- DAQ being brought down for upgrade. DAQ IoC doesn't seem to be cNeed to get Mike and Dan talking to the JF kit...IoC on top of PSI script
- eGun installed in Marietta....need to buy HiCube 80.
- KP:
- Working procedures/calibration with Philip.
- Working docs with Silke for online access.
|
5 min | Budget Update | mmck | - M&S Status (Through December)
- Labor snapshot (Dec. actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business | | |
Action items
- Action: Kazutaka Nakahara to circulate and/or post chiller manual to confluence.
- Action: Kazutaka Nakahara to run chiller over weekend to check stability, IOC performance.
- Action: Group to review ePix cal/comm status on Monday’s call and need for escalation.
- Action: Conny Hansson to look through Philip’s checklists to refine a written JF commissioning plan.
- Action: Zimmerman, Kayla to provide update on the e-gun/RP JSA approval status.
- Action: Zimmerman, Kayla to write up a draft epix10k deployment JSA, based on step-by-step.
- Action: Rebecca to rough out Concept Design for June 26 review.