Set and status planning activities for detector development and deployment.
Discussion items
Time
Item
Who
Notes
30 min
Status
All
ePix Update:
ePixHR:
Carrier PCB board required for testing the HR ASIC has been completed and is now in fab.
PCB will be back next week and we will bond the chips
Testing will start the week after
Mechanical housing of the HR camera (140k equivalent) will be complete in the next week and a half.
ePixM
Layout of ePixM LFoundry complete (3 variants full size)
Layout of test structures almost complete
Fabrication should start around the end of next week
Phase III was approved at PEC on Friday, re-planned to deliver working prototype for downselect vs. VFCCD in late 2020.
Kickoff meeting for ePix fab April 3
Peter Denes visited last week to discuss SXR imager requirements:
Peter wanted to express requirements rather than simple specifications. Document prepared and circulating for review. Comments by end of this week please.
TES re-baseline document has been prepared and is in review by LCLS. Will circulate for comment once strategy is agreed. Year 3 contract funding at CU turned on.
We have a costed proposal from Anton for MCP/TImepix tests...need to get this moving, may ask for some review comments.
Update > Status RIXS-CCD test planning
Masks not here yet, checking with Sallie.
Ground issues resolved from first test?
Late March slips to mid-April??
Do first test at SSRL to decouple from ASC sked??
Status:
MEC EMP testing CSPAD/ePix Date TBD
PH gone first week April
KN Wave8 upgrade for FIM CDR Mid-April
ePix10k requires new MPODS, working issue
Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks)
KZ: Control room furniture install this afternoon.
Vacuum equipment moving today w/techs.
Riggers set for Thursday 10am.
Status documentation/procedures effort
How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 min
Budget Update
mmck
ASC: $222k spent, $31k remains
Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 min
Review ASC First Projects
all
Coordinate/update lab schedule
10 min
Any other business
Action items
Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster