Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll

 

ePix Update:

    • ePixHR:
      • Carrier PCB board required for testing the HR ASIC has been completed and is now in fab.
      • PCB will be back next week and we will bond the chips
      • Testing will start the week after
      • Mechanical housing of the HR camera (140k equivalent) will be complete in the next week and a half.

    • ePixM
      • Layout of ePixM LFoundry complete (3 variants full size)
      • Layout of test structures almost complete
      • Fabrication should start around the end of next week
      • Phase III was approved at PEC on Friday, re-planned to deliver working prototype for downselect vs. VFCCD in late 2020.
    • Kickoff meeting for ePix fab April 3


  • Peter Denes visited last week to discuss SXR imager requirements:
      • Peter wanted to express requirements rather than simple specifications. Document prepared and circulating for review. Comments by end of this week please.
  • TES re-baseline document has been prepared and is in review by LCLS. Will circulate for comment once strategy is agreed. Year 3 contract funding at CU turned on.

  • We have a costed proposal from Anton for MCP/TImepix tests...need to get this moving, may ask for some review comments.

  • Update > Status RIXS-CCD test planning
    • Masks not here yet, checking with Sallie.
    • Ground issues resolved from first test?
    • Late March slips to mid-April??
    • Do first test at SSRL to decouple from ASC sked??

Status:


  • MEC EMP testing CSPAD/ePix Date TBD
  • PH gone first week April
  • KN Wave8 upgrade for FIM CDR Mid-April
  • ePix10k requires new MPODS, working issue
  • Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
  • eGun interlock doc (2wk.)
  • Lost cabinets were not delivered....(2wks)
  • KZ: Control room furniture install this afternoon.
  • Vacuum equipment moving today w/techs.
  • Riggers set for Thursday 10am.
  • Status documentation/procedures effort
  • How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 minBudget Updatemmck
  • ASC: $222k spent, $31k remains
  • Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 minReview ASC First Projectsall

Coordinate/update lab schedule

10 minAny other business  

Action items

  • Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster