TES re-baseline document has been prepared and is in review by LCLS. Will circulate for comment once strategy is agreed. Year 3 contract funding at CU turned on.
We have a costed proposal from Anton for MCP/TImepix tests...need to get this moving, may ask for some review comments.
Update > Status RIXS-CCD test planning
Masks not here yet, checking with Sallie.
Ground issues resolved from first test?
Late March slips to mid-April??
Do first test at SSRL to decouple from ASC sked??
Status:
MEC EMP testing CSPAD/ePix Date TBD
PH gone first week April
KN Wave8 upgrade for FIM CDR Mid-April
ePix10k requires new MPODS, working issue
Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks)
KZ: Control room furniture install this afternoon.
Vacuum equipment moving today w/techs.
Riggers set for Thursday 10am.
Status documentation/procedures effort
How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 min
Budget Update
mmck
ASC: $222k spent, $31k remains
Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 min
Review ASC First Projects
all
Coordinate/update lab schedule
10 min
Any other business
Action items
Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster