Time | Item | Who | Notes |
---|
30 min | Status | All | ePix Update: - Kickoff meeting for ePix fab April 3
- Peter Denes visited last week to discuss SXR imager requirements:
- TES re-baseline document has been prepared and is in review by LCLS. Will circulate for comment once strategy is agreed. Year 3 contract funding at CU turned on.
- We have a costed proposal from Anton for MCP/TImepix tests...need to get this moving, may ask for some review comments.
- Update > Status RIXS-CCD test planning
- Masks not here yet, checking with Sallie.
- Ground issues resolved from first test?
- Late March slips to mid-April??
- Do first test at SSRL to decouple from ASC sked??
Status:
- MEC EMP testing CSPAD/ePix Date TBD
- PH gone first week April
- KN Wave8 upgrade for FIM CDR Mid-April
- ePix10k requires new MPODS, working issue
- Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
- eGun interlock doc (2wk.)
- Lost cabinets were not delivered....(2wks)
- KZ: Control room furniture install this afternoon.
- Vacuum equipment moving today w/techs.
- Riggers set for Thursday 10am.
- Status documentation/procedures effort
- How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
|
5 min | Budget Update | mmck | - ASC: $222k spent, $31k remains
- Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule |
10 min | Any other business | | |