LCLS Magnet Controls
Documents
...
Operations
...
Magnetic Measurements
Magnets Installation in the tunnel
Commissioning
Magnet Power Supply and Controls Schedule |
---|
Injector and BC1 | |
---|
[ Cost and Schedule | http://www.slac.stanford.edu/grp/lcls/controls/global/subsystems/magnet/presentations/FDR/hw/Injector%20and%20BC1/lcls_mgnt_inj_bc1_cost_and_schedule.ppt ] |
| [ Software Schedule | LCLS Magnet Software Schedule ] |
| [ Old Web Pagehttp://www.slac.stanford.edu/grp/lcls/controls/global/subsystems/mgnt/schedule.htm ]) |
[ Installation Schedule (PDF) | tiki-download_wiki_attachment.php?attId=127 ] |
| [ Cable Plant | http://www.slac.stanford.edu/grp/lcls/controls/global/installation/LCLS%20S20%20%20S21%20Cable%20Plant%20Ph2%20R1.mpp ] | |
[ Downtime Schedule for 2006http://www.slac.stanford.edu/grp/lcls/controls/global/installation/2006%20DOWN%20TIME%20Sched%2008-03-06%20Area%20Mgrs%20scheds%20R2.xls ] |
BC2 |
---|
| [ Installation Schedule (PDF) | tiki-download_wiki_attachment.php?attId=129 ] | |
Downtime Schedule for 2007 |
| Downtime Schedule for April 14-25, 2008 |
Phase IV | |
[ Installation Schedule (.mpp)https://slacspace.slac.stanford.edu/sites/LCLS%20Document%20Storage/01%20-%20LCLS%20Systems/electronbeamsys/mag/magpwrsupp/Magnet%20List%20by%20PS/1/LCLS%20Power%20Supply%20Installation%20Phase_4%20r4.mpp ] |
| Downtime Schedule for 2008 |
...
- Bench
- Pre-Installation - Begins July 24, 2006 in bld24
- Integration and System Checkout - Oct 10, 2006
- Commissioning - Begins Jan 3, 2007
...