This page contains the Magnet Controls Software Schedulefor the Injector and BC1.

Driver and Device Support

Start Date: 01-Mar-06

Bus Type*: *VME

Module

I/O Type

Num Of Weeks

Date Needed

Status

Assigned To

Acromag IP-440

DI

1-hour

20-Mar-06

done

S. Allison

Acromag IP-445

DO

1-hour

20-Mar-06

done

S. Allison

Acromag AVME9670

IP Carrier

1-hour

20-Mar-06

done

S. Allison

Acromag IP-231

DAC

2-day

20-Mar-06

in progress

K. Luchini

Hytec IP-8402

DAC

2-days

20-Mar-06

in progress

K. Luchini

Hytec IP-8413

ADC

2-days

15-Jul-06

Not Avail

K. Luchini

BiRa VSAM 7305

Scanning ADC

2-day

20-Mar-06

done

K. Luchini

Record Support

Start Date: 01-Mar-06

Type

Num Of Weeks

Date Needed

Status

Assigned To

VME Card

1-hour

20-Mar-06

done

K. Luchini

EDM Display Mockups

Start Date: 01-Mar-06

Description

Num of Weeks

Date Needed

Status

Assigned To

Single Unit

2-days

17-Mar-06

in progress

K. Luchini

Module Diag

2-days

17-Mar-06

in progress

K. Luchini

XCOR Units

2-days

17-Mar-06

done

D. Rogind

All Units

2-days

17-Mar-06

in process

D. Rogind

Standardize

2-days

17-Mar-06

done

D. Rogind

Summary Status

2-days

02-Apr-06

TBD

TBA

Diagnostic

2-days

02-Apr-06

TBD

TBA

Calibratin Diag

2-days

01-Jul-06

TBD

TBA

History Plot

2-days

01-Jul-06

TBD

TBA

Correlation Plot

2-days

01-Jul-06

TBD

TBA

Strip Charts

2-days

01-Jul-06

TBD

TBA

EDM Displays

Start Date: 01-Mar-06

Description

Num of Weeks

Date Needed

Status

Assigned To

SCP Panels

Start Date: 01-Jul-05

Num of Weeks: 1

Description

Micro

New/Existing

Filename

Date Needed

Status

Assigned To

Dev Micro Units

XL01

N

MGNTXL01.PNL

10-Sep-05

done

J. Paz

Dev Micro Units

XL02

N

MGNTXL02.PNL

10-Sep-05

done

J. Paz

Dev XL03 Units

XL03

N

MGNTXL03.PNL

10-Sep-05

done

J. Paz

Dev XL04 Units

XL04

N

MGNTXL04.PNL

10-Sep-05

done

J. Paz

Dev XL05 Unitx

XL05

N

MGNTXL05.PNL

10-sep-05

done

J. Paz

Dev Template

XLXX

N

MGNTXLXX.PNL

10-Sep-05

done

J. Paz

Injector Units

IM20

N

MGNTIM20.PNL

03-Jan-06

done

J. Paz

Linac S21 Units

LM21

E

MGNTLM21.PNL

03-Jan-06

 

J. Paz

Linac S24 Units

LM24

E

MGNTLM24.PNL

03-Jan-06

 

J. Paz

Linac S25 Units

LM20

E

MGNTLM20.PNL

03-Jan-07

 

J. Paz

BSY Units

BM01

E

MGNTBM01.PNL

03-Jan-07

 

J. Paz

EPICS Database

Task

Add records needed by the complicated actions (standardization, calibration, degauss, trim) (inputs and output, including status).

Add more "control" records (ie, one bo record per applicable control bit in HSTA)

Add records that combine control records into HSTA and translate HSTA into control records.

Add records that combine the action statuses and various record severities into STAT.

Add logic needed for polarity.

Add diagnostic records (ie, compress records to keep the last x readbacks, etc)

Change to allow the same polynomial coefficients to be used in multiple devices.

Changes for magnets on a string (ie, no control available per device)

Feedback status and diagnostic records per device.

Control, status, and processing records per feedback loop.

Records to contain feedback loop incoming measurements.

Periodic update of alarm limits to catch when BDES is changed without a trim or perturb.

Records that perform actions on groups of devices ("ALL*" functionality).

Create better templates per device type (BEND, LGPS, COR,