See Thermal Tests (confluence page) for links and information on the studies done so far at SLAC for Thermal Testing (and related instrumentation).

Manual for VFD:  https://www.hitachi.us/supportingdocs/forbus/inverters/Support/WJ200_Instruction_NT325X.pdf

CO2 Operation harzard table is here

The spreadsheet for operating CO2 system is here

===========================================================================================================================================================

QC Test Box XY Stages

01:02 AM May 22, 2021: UNDER DEVELOPMENT BY SANHA (This section serves as a documentation as well as an e-log, while the system is still under development.)

This section documents the set-up and the operation of the XY stages (one for the ring and the other for the stave) in the QC test box.

Contact: Sanha Cheong (sanha@slac.stanford.edu)


DCS & Monitoring

Contact: Valentina Cairo (vcairo@slacContacts: Sanha Cheong (sanha@slac.stanford.edu) , Zhi Zheng (zzheng@slac& Matthias Wittgen (wittgen@slac.stanford.edu)

Set-up Overview

Image Removed

The stages are powered OpenBuilds 24V DC power supplies inside the QC test box. They are also connected via USB to the iMac (running Ubuntu) next to the QC text box and can be controlled by `OpenBuilds CONTROL` software.

Operation & Calibration Procedures

Ring Stage

USB0, Left PS

X: + is down, - is up. steps / mm = 197.04

Y: + is in, - is out. steps / mm = 57.14

Interlocks: X = [-5.21mm, 263mm] Y = [-5.18mm, 410mm]