SVT EPICS Power Instructions

DAQ Mapping in Group C

HPS 2014 SVT Group C Setup

All operations are from hpstracker in group C. 

Operation

!!! Remember to make sure the detector is being cooled. !!!

!!! Remember to make sure the interlocks are in the state you want them. !!!

SVT EPICS Power Instructions

Basic instructions to take a pedestal run with CODA

To be added.

 

 

MPOD Power Map

Table as of 11/17/2014 

GUI FEB IDPhysical FEBStatusComment
0L1t

OK

 
1

L2-3t

OK 
2L5tOK 
3L6tOK 
4L4tOKThese should be checked!
5L4bOK
6L5bOK 
7L6bDIG bad (Y-cable problem?) 
8L2-3bOK 
9L1bShort on AVDD? 
GUI Flange IDPhysical Flange BoardStatus
01 (top)OK
12OK
23OK
34 (bottom)OK

 

...

Miscellaneous

Reloading PGP card drivers

...

$ cd /u1/pgpcard/software/driver_old/

$ ./pgpcard_load






 

OLD:Take a calibration run with expert SVT GUI

 

Start the DAQ:

 

$ cd /u1/software/software_new

...