Text in the excerpt box will show up in lists of meetings.FESAC white paper on major facilities. Early science with threshold KPPs. Cost scales for measurement innovation BRN
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
Walk-in | Question about DR output and what engineers are doing What is the time frame for projecting forward to cost savings? → Jama requirements exercise: will there be a review and release? → not a wholesale reset Precluding of second petawatt: science cases / detail in CDR
| ||
Scope reduction conversations / workshopping |
| ||
Laser systems considerations and changes | This was discussed last meeting. Just some additional opportunity (ROD 23) Design is going to preclude the second petawatt as an upgrade option if DMPL is realized. | ||
Measurement innovation workshop follow-ups | Categories 1 and 2 cost scales | ||
UAP | Rick Kraus, now at UNR, will be our new chair. Working next week to spin back up the UAP, including drop offs and new members. | ||
Science below objective KPPs (flagship implications) | Short pulse threshold 30J in 300 fs consider, say 50J at 200 fs: 3x less energy, 4x less intensity
Long pulse threshold 100 J; say 500 J for sub-objective
| ||
Experiments for project completion, day 1, year 2, and year 5 descriptions | Consider the example of MEC's commissioning / early science as a baseline. Eric M Galtier or Bob Nagler can review.
Could also look to the XFEL example. |