Time | Item | Who | Notes |
---|
10 min | Beamtime support update |
| - Detector readiness:
- Return ePix100#7 for repair?
- Receive/test ePix100 spares and side-look 1mm ePix10k
- Baseline JF and 2M 'traveller' pages on Confluence.
- Collect and analyze any remaining in-lab test data.
|
30 min | Priorities Review | All | - 2021 events:
- Projects new starts:
- VFCCD/ePixM downselect → implementation of REXS for 2.2 - April 28-30
- Panel charge draft finalized, panel set, website set up.
- SparkPix-S Phase II (full-size ASIC for sparsification, Tixel-based, underway)
- ePixHR IV: Prototype detector project underway
- TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) CDR Closed out, project underway.
- ePixUHR (130nm TSV structure to reach 100kHz), planning
- Production:
- spare modules (0.5 & 1mm) Module order in work, new sensor order out
- Approved 3d copy of ePix10k2m: PA code issued, work begins
- Approved spare quads for MEC: PA Code issued, work begins
- Proposed in-vac ePix10k2m for CXI: Need FY21 cost split, likely to go forward
- Proposed ePix10k4m (concept)
- Proposed UED detector upgrade (2kHz, 125um sensor)
- RIXS-CCD/cooler test and verification (cooler and packaged supply tested at STA). Engineering note released.
- HiZ collaboration tests (IH secured, plans circulated to collaboration partners), met w/SSRL, LoI needed
- Outreach for R&D support (SparkPix-ED, SparkPix Delta).
- Support effort for LCLS-II-HE instruments (performance verification/implementation planning)
- SBIR effort for UXI.
- Group priorities review:
- Testing
- Setup ePix10k, ePix100, JF smalls for test in lab, Bhavna/Chris hands-on trng. Day this week?
- Review with TID the stitching progress, look for improvements. Stand up calibration team
- Can we figure out what's wrong with ePix100/7?
- RIXS-CCD cooler test planning.
- Analysis
- Gather and process relevant commissioning data for Mp travellers on Confluence.
- Solid pedestals
- Noise map
- Response uniformity (mini-X cu-fluorescence)
- Bootstrap gain (sealed source)
- Linearity (signal injection)
- Documentation
- Complete on-line travellers for Mp detectors
- Development
- RIXS-CCD, review engineering note with w/NEH 2.2
- SXR Downselect prep. May 1?
- Lab 'commissioning'
- DAQ
- Storage nodes received
- LCLS I/II compatibility?
- BIO for racks in chase (Chris to take over hounding)
- Vac chamber for in-lab tests? Compatible with XPP alcove?
Actions:
|
30 min | Status |
| IFDEPS Virtual Thursdays Tech mtg w/TID today Issues with UED pedestals/corrections Cal status summary pls,
CH: - ePix10k #1 has been tested, looks ok
- pyROOT for per-pixel spectra
- Synchrotron.
RA: - Meeting w/PD tmrw, camera.
- Need bake-out variac for lab.
KN: - Rayonix still cranky trigger, may be DAQ-related
- Spare JF Power supply received, need cold plate.
- UED MPOD?
- Rayonix has two bad tiles, too close to experiment to fix.
PH: - MFX 10k calibration with hockey stick has been refined slightly..2% of pixels have noisy first switch, need more uptime to test.
- UXI IoC update, need help from Dan to run in the lab.
BN: - Made updates to detector website, in work.
- working with PH on porting PyRoot to Python.
CK: - Ge chamber assembly
- Order variac
- New pin-out probes
- XPP having trouble with pgp server hat runs 2M.
- CXI fiber 450uW becomes 50-60uW, defect in port feedthrough sometime limits to 2uW(?), replacement flanges on order (8-9 weeks).
|
5 min | Budget Update | mmck | - M&S Status (Through December)
- Labor snapshot (December actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business |
|
|