Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minDeployment 3-wk planTeam

Plans to support upcoming experiments.

  • Wave8 testing this week, yes, but later this week? Body count in lab near limit.
  • Maciej firmware update on 2M.0? Complete XCS deployment?
  • Jungfrau testing this week...when vacuum?
  • Smalls injection code status??
  • Constants generation/deployment status? Are we happy with sate of ePix cal?
  • This week's commissioning:
    • Rayonix Status?):

      Jungfrau (CXI):
      - W 12 August, 9pm - 5am: Jungfrau/CSPAD Cal/Commissioning
      - Th 13 August, 9pm – 3am: Jungfrau/CSPAD Cal/Commissioning
      - F 14 August, 9pm – 3am: Jungfrau/CSPAD Cal/Commissioning

      • Set up pre-beam testing to complete NLT week of Aug 1 (Instrument team meetings)

    • ePix10k2M.1 (MFX):
      - Sa 8 August, 9am – 9pm: ePix10k

      • Set up pre-beam testing to complete NLT week of Aug 1 (Instrument team meetings)
    • ePix10k2M.1 (XCS):
      - F 7 August, 9am – 3pm: ePix10k

      • Set up pre-beam testing to complete NLT week of Aug 1 (Instrument team meetings)
  • Baseline JF and 2M 'traveller' pages on Confluence.
    • Collect and analyze any remaining in-lab test data.
      • Solid pedestals
      • Noise map
      • Response uniformity (mini-X)
      • Bootstrap gain (sealed source)
      • Linearity (signal injection)
      • Document results in 'traveller' on confluence
    • Next detector deployed: Kayla to lead meeting for mapping detectors to experiments.
30 minStatusAll
  • Group priorities review:
    • Detectors for Run 18
      • Jungfrau commissioning plan and commissioning tests.
      • ePix10k2M (new) Commissioning test plan, calibration along same lines as JF.
      • ePix10k2M (old) Needs shroud re-replaced, plans for backplate replacement.
      • ePix smalls tests to match.

    • Detectors under development
      • RIXS-CCD, review draft Project Plan w/NEH 2.2
      • RIXS-CCD Concept Design (R to set meeting to talk cooling options)
      • Anton project at UCB/SSL (milestone/schedule revision received)
      • SXR Downselect prep

    • Lab 'commissioning'
      • DAQ
        • Storage nodes
        • LCLS I/II compatibility
      • Table seismic
      • Laser table re-cert
      • BIO for racks in chase
      • DP node purchase
      • Sealed source purchase (M&S evaporating)


Actions:

    • check with TID about status of small epix100/10ka. (Mark, query sent)
    • check what cables we need for the in-vac epix100 setup in MEC and CXI. (Philip)
    • Laser recertification (Kaz)
    • Wave8-V2 tests (Kaz)

Other news:

ePix10k2M calibration/communication progress continues, escalation necessary?

CH: USB patch cord available??

  • Mask measurements last week.
  • Project management training.
  • Charge injection scripts on 10k smalls for mask tests.

 

RA: Beam pipes for 2M? In work.

  • Loan stages to CXI....ensure return.
  • Meet re cooling concepts...met with Jim re outside space: not much.

 

KP: JSA summary list circulated

  • Small Rayonix to be tested in XPP...manual available??
  • XPP/MFX/XCS fibers due this week, other wise need ugly solution.
  • Small Rayonix testing can be done by others.
  • XPP/XCS power cable pinout (controls needs to tell us MPOD working)

 

PH:

  • Learning NERSC interface

 

 

 

 

5 minBudget Updatemmck
  • M&S Status (Through June)



  • Labor snapshot (June actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items