LCLS Estimated IOC Count for Injector and BC1
Table 1.1 lists the minimum number of VME CPU's that will be needed for system test May 21, 2006.
Table: 1.1 |
Area: Injector and BC1 |
Date Needed: May 21, 2006 |
Subsystem |
Assigned To |
MVME6100 |
MVME5500 |
BPMs |
T. Straumann |
? |
? |
Collimators |
S. Peng |
? |
? |
Fast Feedback |
D. Fairley |
? |
? |
Laser Steering |
S. Peng |
7 |
1 |
LLRF |
D. Kotturi |
0 |
0 |
Magnets |
K. Luchini |
0 |
1 |
MPS I |
S. Norum |
? |
? |
MPS II |
A. Alarcon |
1 |
0 |
PPS |
Alarcon |
1 |
0 |
BCS |
Alarcon |
3 |
0 |
Timing |
D. Kotturi |
2 |
0 |
Toroids |
S.Peng |
1 |
0 |
OTR/YAG |
S. Peng |
9 |
0 |
Wire Scanners |
D. Murray |
2 |
0 |
Vacuum |
S. Schuh |
? |
? |
Table 1.2 lists the number of VME CPU's in-house as of March 9, 2006.
Table: 1.2 |
SLAC PO: [ 54842 |
https://www-bis.slac.stanford.edu/slaconly/bin/purdetail.asp?ISREQ=yes&ID=0000115984 ] [ 58362 |
https://www-bis.slac.stanford.edu/slaconly/bin/purdetail.asp?isreq=yes&id=119773 ][ 57669 |
https://www-bis.slac.stanford.edu/slaconly/bin/purdetail.asp?isreq=yes&id=118962 ] |
Model |
Qty |
MVME6100 |
11 |
MVME5500 |
9 |
Synergy PPC |
?? |