  1.  ePixM:
    1. Beamtime prep, Status:
      1. Install the ePixM at MFX beam dump
        • Scheduled Time: Thursday, September 26, 12 pm - 2 pm.
        • Setup check list: Fiber converter (with FTP fiber and 3 tranceivers), Power supply, Keithley Source meter (TID IC lab), power cable
        • Before the deployment, check the fit of the masks with the detector unit shell.
        • Check the MFX hutch Humidity/Temp sensor to calulate the Dew point.
      2. Move the setup to the beamtime table
        1. Next Monday 11am
        2. Physical setup to secure the camera; (Chris Koerber)
      3. Test the script for the beamtime data collection;
        • Git branch update?
      4. Setting up the pre-setup meeting (include TID people);
      5. LCLS Daq for beamtime
        1. New register setting optimized for dynamic range
      6. Get the measurement plan (Zongde)
      7. Schedule the staffing;
        • Two-person hutch searching  required 
        • Philip will be online for the first shift and on call for the second shift.