Attendees: Gilliss Dyer Mikael David Martinez Walter Wittmer Ginger DeContreras LaFortune, Kai Nicholas Pointing stability; getting on the same page with LLNL; working on ops model; alternate flagships for alternate laser
Discussion items
Item | Notes |
---|---|
2nd Petawatt | MM: Write up where we are on 2nd Petawatt. Adding would require construction and heavy reconfiguration. Pre-concept, and we cannot execute design right now. Science team needs to message 2nd Petawatt in general. |
RR-SP pointing stability | |
Radiation Source Term | |
Spatial Chirp | Can we run with and without spatial chirp? Why high cost of moving grating? Gilliss - can we quantify what's happening at the beam at target (spatiotemporal)? Need a description at near focus. Reduce fluence. What safety factor are they planning for? Impact of spatial chirp + wavefront error? Desire for being able to dial out spatial chirp. Gilliss - we should write down Bill's thoughts and ask LLNL to perform analysis. Need technical note. MM: We need to be careful about asking LLNL to perform tasks that are out of scope. Gilliss - need details of compressor design. What software do we need to model properly? Gilliss - Nick side note - ELI MP is very stable (Thalus). |
Global Requirements Workshop | May 8, 9 or 10. Purpose is to confirm requirements and revisit particularly challenging requirements. MM: Any other reviewers? Gilliss: Recommends reviewer from Omega. Hans. Gilliss: One of top priorities (before parental leave) to get GRD into Jama. |
Topics for Next Time
- Document Radiation Source Term assumptions
Action items
- LaFortune, Kai Nicholas RR-SP pointing stability - revisit stability budgets and assumptions. (on hold)
- LaFortune, Kai Nicholas Turn slide deck into Engineering Note and publish. (on hold)
- Mikael David Martinez to send LLNL presentation to LaFortune, Kai Nicholas Ginger DeContreras . (on hold)
- Ginger DeContreras to consolidate into TN. (on hold)
- Hardin, Corey L. Put together material for Mikael to brief Mike Dunne by 3/20/2024. Leverage slides/images from Facility Stress Test Workshop (vestibule/beam transport lines on 2nd floor, etc.)