Attendees: 

Alex Wallace Barry Fishler Nate Landis Barry Fishler Jing Yin Yang, Steven Peregrine McGehee John Cline Randy Sanchez Tom Spinka Jasmine, Nguyen Tamas Winkler Ricardo Martinez Martinez Govednik, Janez Gregory Brent 

Meeting Agenda

Previous Meeting Notes: 2023-09-19 MEC-U Project Controls and Data Systems Team Meetings

 

Approx. Time

Agenda ItemLinksNotes

50 min 

  • DR Prep - Review FAC Recommendations, P6, and Worry List.
    • 1.02 and 1.04 coordinate recommendations to address during DR. 
    • Are there gaps or inconsistencies in P6 schedule for control? Any issue in control worry list that still need to be addressed?

FAC Recommendations

Worry List

P6 Schedule 


FAC Recommendations 

  • Reviewed FAC recommendations and wrote notes for all entries.
  • Some were transferred from Jing to Alex so that he can address them at the DR. 
  • Barry and Nate's input is needed for cosylab effort estimates. Alex will present efforts and estimates for cosylab at DR. 
  • Steven reviewed his recommendations and did not find any that overlap with controls. 

Worry List

  • We did not review worry list since we are doing this at the technical integration meetings. 

P6

  • Steven had some confusion on laser design scope in 1.04, but we clarified that it was for laser integration. Jing will get this adjusted in the next release. 

10 min 

  • Check in on laydown slides.
    • Expectation to have slides created and some of the title slides inputted.  
    • How should we split up presentation of control scope, schedule, and cost between Alex, Jing, Nate, Barry and Steven.

Presentation Folder: SC-3 Controls and Data Systems

DR Prep Site

  • We did a brief check-in on the template, but due to time constraints we are pushing this to a separate meeting time for next Monday, at 11am. 

Next Meeting

Date

Objectives


 

  • Continue check in on slide laydown in preparation for laydown review  

Presentation Folder: SC-3 Controls and Data Systems

DR Prep Site


 

  • Continue DAQ discussions.
    • If able, begin writing up some requirements on what the DAQ should provide to the laser systems. 
IT Infrastructure Build Requirements Spreadsheet

Action Items:

DescriptionDue dateAssigneeTask appears on
  • Require concept for toggling power on/off to small motors (CosyLab contacted)
MEC-U Collective Team Meetings
  • Seeking existing SLAC solution for closed loop pointing stability loop (vision/motor)
MEC-U Collective Team Meetings
  • Require concept for toggling power on/off to GigE cameras (CosyLab contacted)
MEC-U Collective Team Meetings
  • Omar Quijano To work on documenting SLAC's IT infrastructure design including hardware specs and key information.
Omar Quijano2023-02-21 MEC-U Project Controls and Data Systems Team Meetings
  • Terzi, Ken To adjust some items on the presentation then send out to the group and Omar. Mitchell Cabral Will upload this to the Sharepoint.
Terzi, Ken2023-02-21 MEC-U Project Controls and Data Systems Team Meetings
Barry FishlerSet Point API WG pt.2
  • Jing Yin TPR Card Specification Stub (Specific question from Ken: Number of outputs for TTL? LVTTL or TTL? Both?)
Jing Yin2023-02-07 MEC-U Project Controls and Data Systems Team Meetings
Tyler Johnson2022-11-14 MEC-U Project Controls and Data Systems Team Meetings
  • SLAC to provide GUI standards for laser systems (standards in development.). Follow up. Mitchell Cabral 
Mitchell Cabral2022-11-03 MECU LLNL/SLAC Meeting
  • LLNL to share C++ standards for SLAC review. Follow up. Vinod Gopalan
Vinod Gopalan2022-11-03 MECU LLNL/SLAC Meeting


  • No labels