Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
10 minBeamtime support update
  • No experiments until Saturday 1/30
  • Detector readiness:
    • Monitor 2m repairs at TID
    • Monitor quad repairs at TID (one quad returned)
    • Send ePix100#7 for repair
    • Receive/test ePix100 spares and side-look 1mm ePix10k
    • Baseline JF and 2M 'traveller' pages on Confluence.
      • Collect and analyze any remaining in-lab test data.
30 minPriorities ReviewAll
  • 2021 events:
    • Projects new starts:
      • VFCCD/ePixM downselect → implementation of REXS for 2.2 -Late April
      • SparkPix-S Phase II (full-size ASIC for sparsification, Tixel-based) PEC today
      • ePixHR IV:  Prototype detector
      • TXI Detectors (2Mp and 140kp based on ePixHR @5kHz) CDR tmw
      • ePixUHR (130nm TSV structure to reach 100kHz)
    • Production:
      • spare modules (0.5 & 1mm) Module order in work
      • Proposed 3d copy of ePix10k2m (pending)
      • Proposed spare quads for MEC (2)
      • Proposed in-vac ePix10k2m for CXI
      • Proposed UED detector upgrade (2kHz, 125um sensor)
    • RIXS-CCD/cooler test and verification.
    • HiZ collaboration tests.
    • Outreach for R&D support (SparkPix-ED, SparkPix Delta).
    • Support effort for LCLS-II-HE instruments (performance verification/implementation planning)
    • SBIR effort for UXI.


  • Group priorities review:
    • Testing
      • Setup ePix10k, ePix100, JF smalls for test in lab
      • Review with TID the stitching progress, look for improvements.
      • Can we figure out what's wrong with ePix100/7?
      • RIXS-CCD cooler test/ship plan
    • Analysis
      • Gather and process relevant commissioning data for Mp travellers on Confluence.
          • Solid pedestals
          • Noise map
          • Response uniformity (mini-X cu-fluorescence)
          • Bootstrap gain (sealed source)
          • Linearity (signal injection)
    • Documentation
      • Complete on-line travellers for Mp detectors

    • Development
      • RIXS-CCD, review engineering note with w/NEH 2.2 
      • SXR Downselect prep.  May 1?

    • Lab 'commissioning'
      • DAQ
        • Storage nodes
        • LCLS I/II compatibility
      • Table seismic
      • BIO for racks in chase
      • DP node purchase


Actions:


30 minStatus
  • Case surge anticipated in January, extra absence. All hands update coming.
  • Avoid being at lab first two weeks of Jan. One person per day?
  • Focus on remote data analysis as possible.

CH: 

  • Conference last week, uploaded some talks
  • Meeting w/Chris Iniewski, RAL folks.


RA: 

  • Meet re cooling concepts...met with Jim re outside space: not much.


KP: JSA summary list circulated

  • XPP/MFX/XCS fibers due this week, other wise need ugly solution.
  • Small Rayonix testing can be done by others.
  • XPP/XCS power cable pinout (controls needs to tell us MPOD working)


KN:

  • ePix100 scan for use in run18...Diling has preferences.
  • HV cables done, re-install @CXI.  Matt found defect in a fiber feedthrough.
  • CXI ePix ran fine in ASC over the weekend.
  • Grabbing JF modules for test in lab, but need power supply board from PSI.
  • IOC


PH:

  • MEC deployment, can't read back data from one quad.
  • Circular connectors tough to release...special tool?
  • EMP shielding for in-vac cables isn't tight at connector...revise?
  • UXI IoC update.
  • w/Bhavna & Frederic regarding commissioning data.


BN:

  • Got code working, now need to le it run on some data....
  • Lab visit week of thanksgiving, January moving.

Thursday updates:


PH

  • UXI
  • One quad at MEC had wrong event code, set in expert panel edit traveler for event codes
  • Working to understand LV44 data…looks like photons are causing the ‘spikes’ in fourier space


KN

  • Sunday MFX finishes, 2M comes off, box delivered to MFX today.
  • XPP having trouble with pgp server hat runs 2M.
  • CXI fiber 450uW becomes 50-60uW, defect in port feedthrough sometime limits to 2uW(?), replacement flanges on order (8-9 weeks).


CH

  • Measurements on sm 10k, pedestal application inconsistent in online ami, raw data is fine.
  • Still see dashed lines in pedestal config.


KP

  • Bhavna JSA
  • BIO for move
  • Arranging setup lab
  • move mobile rack o XPP alcove
5 minBudget Updatemmck
  • M&S Status (Through July)



  • Labor snapshot (June actuals):


15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business

Action items: