30 min | Deployment 3-wk plan | Team | Plans to support upcoming experiments. - Wave8 testing this week, yes, but later this week? Body count in lab near limit.
- Wednesday in-lab: Maciej working remotely on 2M fw. Collecting hardware for XCS deployment tmrw afternoon. (pinouts? MPOD/DAQ cmnds?)
- Jungfrau beam tomorrow? Staffing?
- Mask testing done??
- Resolve remaining ePix10k calibration issues NLT week of July 27 (in work).
- Commissioning shifts as presently scheduled:
Rayonix: Jungfrau (CXI): - W 12 August, 9pm - 5am: Jungfrau/CSPAD Cal/Commissioning - Th 13 August, 9pm – 3am: Jungfrau/CSPAD Cal/Commissioning - F 14 August, 9pm – 3am: Jungfrau/CSPAD Cal/Commissioning ePix10k2M.1 (MFX): - Sa 8 August, 9am – 9pm: ePix10k - Set up pre-beam testing to complete NLT week of Aug 1 (Instrument team meetings)
ePix10k2M.1 (XCS): - F 7 August, 9am – 3pm: ePix10k - Set up pre-beam testing to complete NLT week of Aug 1 (Instrument team meetings)
- Baseline JF and 2M 'traveller' pages on Confluence.
- Collect and analyze any remaining in-lab test data.
- Solid pedestals
- Noise map
- Response uniformity (mini-X)
- Bootstrap gain (sealed source)
- Linearity (signal injection)
- Document results in 'traveller' on confluence
- Next detector deployed: Kayla to lead meeting for mapping detectors to experiments.
|
30 min | Status | All | - Group priorities review:
- Detectors for Run 18
- Jungfrau commissioning plan and commissioning tests.
- ePix10k2M (new) Commissioning test plan, calibration along same lines as JF.
- ePix10k2M (old) Needs shroud re-replaced, plans for backplate replacement.
- ePix smalls tests to match.
- Detectors under development
- RIXS-CCD, review draft Project Plan w/NEH 2.2
- RIXS-CCD Concept Design (R to set meeting to talk cooling options)
- Anton project at UCB/SSL (milestone/schedule revision received)
- SXR Downselect prep
- Lab 'commissioning'
- DAQ
- Storage nodes
- LCLS I/II compatibility
- Table seismic
- Laser table re-cert
- BIO for racks in chase
- DP node purchase
- Sealed source purchase (M&S evaporating)
Actions: - check with TID about status of small epix100/10ka. (Mark, query sent)
- check what cables we need for the in-vac epix100 setup in MEC and CXI. (Philip)
- Laser recertification (Kaz)
- Wave8-V2 tests (Kaz)
Other news: ePix10k2M calibration/communication progress continues, escalation necessary?
CH: USB patch cord available?? - Mask measurements last week.
- Project management training.
- Charge injection scripts on 10k smalls for mask tests.
RA: Beam pipes for 2M? In work. - Loan stages to CXI....ensure return.
- Meet re cooling concepts...met with Jim re outside space: not much.
KP: JSA summary list circulated - Small Rayonix to be tested in XPP...manual available??
- Jungfrau ran over weekend...results TBD.
- AMI display doesn't show Jungfrau correctly yet.
- Coordinate w/Alex over Wave8/Rayonix commissioning.
- XPP/MFX/XCS fibers due this week, other wise need ugly solution.
- Small Rayonix testing can be done by others.
- XPP/XCS power cable pinout (controls needs to tell us MPOD working)
PH: - Data analysis: need G Blaj to confirm data issues.
- Learning NERSC interface
|