Set and status planning activities for detector development and deployment.
Discussion items
Time
Item
Who
Notes
30 min
Status
All
ePixM Phase III was approved at PEC on Friday, re-planned to deliver working prototype for downselect vs. VFCCD in late 2020.
1 in-air ePixBig (Jan 2020) and 4 thick-Si MEC (May 2020) quads also approved. Need a kickoff meeting and probably a little more hands-on than first article(?)
Peter Denes visiting tomorrow to discuss SXR imager requirements:
50um pixel pitch
15e- rms read noise
5kHz frame rate or greater
512x512-class pixel format, to be tileable to 1Mp-class with >90% fill factor. Buildup from smaller 4-side buttable modules is acceptable.
1000 photon well capacity @1.5keV530eV
>90%70% QE at 277-1.5keV
High Vacuum compatible (10e-9T)
Compatible with 2m electronics cabling and cooling hoses to allow in-chamber articulation.
Compact packaging for mounting within q-RIXS vacuum chamber (dimensions to be specified, but like iVFCCD concept))
Visible-blind to laser pump background.
Decide ASC electrical after move-in costs known
Rebar scan complete, anchors set(?)....set up ASC coordination meeting (KZ)?
Status JF 4M effort. 4pm meeting today....
Update > Status RIXS-CCD test planning
Masks not here yet, checking with Sallie.
Ground issues resolved from first test?
Late March slips to mid-April??
Do first test at SSRL to decouple from ASC sked??
MEC EMP testing CSPAD/ePix Date TBD
PH gone first week April
KN Wave8 upgrade for FIM CDR one fine day
ePix10k requires new MPODS, working issue
Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks)
KZ: ASC metro technicians are tied up. Scanning today.
Sean and Gibson are scanning. Hole patterns to be marked Wednesday. Drilling/Anchors Th/Fri.
Working with LeRoy
Status documentation/procedures effort
How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 min
Budget Update
mmck
ASC: $191k spent, $62k remains
Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan