Set and status planning activities for detector development and deployment.
Discussion items
Time
Item
Who
Notes
30 min
Status
All
JF4M assembled....servers available? Parts available for assembly beginning 11/22
ePix10k Tested at APS.
Spoke with David regarding wide body RIXS....concerned that scope of integration is not fully understood/accommodated in planning.
Trying to create compelling case for Tixel for September PEC...taking a long time, ongoing.
ePix100s forwarded to TID for refurb?
Need firmware on 10k small to test....status?
SLAC-level Detector Strategy Task Force: SAC presentation went well, SPC this week, then LDAC.
DAQ rack plinth set received, fit questionable.
Seismic table mount components received..to be installed.
LDAC set for Dec. 3-4.
Status of 2018 recommendations: 18 closed/complete, 13 in work/on track, 3 deferred/rejected (Doc available).
NEED:
RIXS-CCD need analysis of flux limitations (status?)
'White paper' on zero-suppression tradeoffs (in work).
Data analysis on ePix prototypes tested in Run 17.
Status:
RA: Establishing clean area....do not touch items on big table without asking RA first.
Need to conclude wiring detail. Each wire should be managed.
Set up a meeting with Dan, Raj to talk over packaging, strain relief.
Time on drawings....progress ongoing. Four of the big 5 are out....still need 3-d part...looking at making two copies to test machining in house....submit by end of week?
PH: Writing RIXS Talk. Submitted two in-house proposals...one on TID sensors, one on UXI@MEC
Also one on thin-crystal heating at CXI.
Need to discuss acquiring sensors from UXI collaboration.
Wiring diagram for Jungfrau (Sameen)
Need automated check on pedestal levels...Jason left and no one has picked up.....PH to follow up with Silke.
UXI options? Nothing until next year....Liam here this week.
Silke to establish a couple of data streams to examine performance on dropped shots etc.
EMP testing confusing, un-grounded CSPAD testing this week...test didn't happen.
Mike Brown has set up ePix10k and ePix100 on XCS for software development...not done?
DAQ can run ePix100, ePix10k, Jungfrau....can't yet save data.
Need to check with Chris about data reduction from Run 17.
KN:
ePix interlock tests done successfully.
Need 7 mode PDUs....lupe to make.
Getting ready for ePixBig test in-hutch on Wednesday to verify hutch is ready to go in Run 18.
Need to get Mike and Dan talking to the JF kit...IoC on top of PSI scripts.
Chicane for Marietta almost ready to install eGun.
Need to coordinate 4-fiber Wave8 with CDS...single vs multimode.
Matt Church helping with Wave8 ?? Need to mount close as possible to flange.
All JF Cables are in work
ePix10k requires new MPODS, working issue...check again mid November.
KZ:
RIXS-CCD Procedure draft complete. Review at next detector meeting??