Scripts will also be ported to rogue 6 and then we will send it to Chris O'grady and Ricciardo
Status sensor
Nothing reported today
Carrier
Heat syncs arrived, need to modify cooling blocks
Tungsten protection ?
we have enough parts for all modules
50 ready to be installed
Mechanics
Extraction tool: Marco to check the status
Long pipes length is defined (from Quentin)
Pipes bent, will be sent out for brazing
Need to drill transceiver heatsink holes
Brazing minimum 2, Bob is bending pipes for it
Action Items
March-13-24
Marco, Dawood and I
Prototypes 2-3
Dawood is working on Rogue 6 updates
Testing is ongoing
Scripts will also be ported to rogue 6 and then we will send it to Chris O'grady and Ricciardo
Status sensor
Nothing reported today
Carrier
Heat syncs arrived, need to modify cooling blocks
Tungsten protection ?
we have enough parts for all modules
50 ready to be installed
Mechanics
Long pipes length is defined (from Quentin)
Brazing minimum 2, Bob is bending pipes for it
Action Items
March-06-24
Prototypes 2-3
Dawood is back next week then he will test the thin entrance window sensor
Status sensor
Sensor are all here
missing copy of the traveler
Test devices were not returned from the vendor. This impacts efficiency measurements. Now this needs to be done on actual sensors. Not sure we can do it at ALS
Radiation damage can still be done
Carrier
Delamination problems persist
Lever arm considered most likely cause. Make tool to insert extract using CK design
Marco will make 2 sets
Tungsten protection
we have enough parts for all modules
50 ready to be installed
Mechanics
Long pipes length is defined (from Quentin)
Brazing minimum 2
Action Items
Complete the flange installing
Complete FW & cable
Pause mechanism implemented by Larry. Dawood needs to test it
HFE tests - probably the best is to test in the new vacuum setup at the ASC
Need to remind the ASC team to performa a vacuum test ASAP
February-14-24
Prototypes 2-3
Dawood is back next week then he will test the thin entrance window sensor
Status sensor
Sensor are all here
missing copy of the traveler
Test devices were not returned from the vendor. This impacts efficiency measurements. Now this needs to be done on actual sensors. Not sure we can do it at ALS
Radiation damage can still be done
Carrier
Delamination problems persist
Lever arm considered most likely cause. Make tool to insert extract using CK design
Marco will make 2 sets
Tungsten protection
we have enough parts for all modules
50 ready to be installed
Mechanics
Long pipes length is defined (from Quentin)
Brazing minimum 2
Action Items
Complete the flange installing
Complete FW & cable
Pause mechanism implemented by Larry. Dawood needs to test it
HFE tests - probably the best is to test in the new vacuum setup at the ASC
Need to remind the ASC team to performa a vacuum test ASAP
January-31-24
Prototypes 2-3
All 3 prototypes are working
Status sensor
Sensor being shipped this week
LF2 and LF3 sensors received
Two carriers sent for wire bonding
missing copy of the traveler
Carrier
Delamination problems persist
Lever arm considered most likely cause. Make tool to insert extract using CK design
Tungsten protection
CK need to have them cut
Delivery at any moment
Flattened and quoted
Mechanics
Complete the 90 Degree while
carrier insertion tool
Action Items
Complete the flange installating
Complete FW & cable
Cut tungsten
HFE tests - probably the best is to test in the new vacuum setup at the ASC
November-29-23
Prototypes 2-3
Assembled this week
FW
Serial, ADC and initialization
Wait for testing
Slow ADC verification (needed for DAQ)
Fast ADC (optional)
Mechanical
Long pipes, still to be done. Change request not approved
Brazing the fittings
Vacuum clean
Goal release boards for final fab
Any missing changes?
Lets check and make a formal review of the changes
Status sensor
Sensor being shipped this week
Bump process started
LF2 - back process has great IvsV curves
Delivery is about 2months after that if yield is high (high risk activity)
115um thick sensor
LF3 will be processed now
Entrance face polished to 1nm.
Last two wafers out for anneal
2 L2 will be out and 1 L3 will be out, procurement is ready
Sent for process
90 L3 V2
30 V1?
New carrier
Change that back to increase the priority here. We need to build a second system for the data systems integration.
Tungsten protection
CK need to have them cut
ETA?
Cooling status
5x 0degree and 5x 90 degree in fab ETA 09/18/23 10/25/23
Get two strong backs assembled with 4 engineer flavor modules 3 units
Get shells fabrication started - not started yet.
Board fab
Dionisio to send email to buyer and his supervisor with Angelo in CC.
Feb-08-23
Status sensor
sensor back processing did not show the needed quality, but look promising
Julie and Chris are improving the recipe for the annealing
Detector delivery sequence
1st detector needed is chemRIXS (from Angelo's feedback), feed back from Giorgi is that he needs to circulate this question again within LCLS and get back to us
Given the uncertainties we should assemble the prototype, we will use the qRIXs to complete the prototype.
Status of electronics boards production
Digital board still on hold from procurements
Carriers - boards are with CK, strong back ready and will be delivered to Chris today.
P&C board with Dan
Status of the mechanical parts
Chiller and cooling lines
REXS lines have been identified
Chiller options, should we buy now.
link for the single detector (needs 3 units)
link to the larger option (serves all 3 detectors)