Attendees:
LaFortune, Kai Nicholas
Yang, Steven
Hill, Elizabeth
Cunningham, Eric Flint
Eric M Galtier
Terzi, Ken
Reagan, Brendan
Ginger DeContreras
Concept of Operations (ConOps)
Intro - Will identify chair and refine charter in future meetings.
Topics | Notes |
---|
Strawman | Roles vs. Macrosteps: Continued to work on this swim lane diagram with input from E. Galtier. - Use average trajectory for all hutches for alignment
- Set accelerator parameters, use slits to set optical path
- HPS checks (gate valves and stoppers)
- Confirm mirror alignment
- Confirm beam path is clear
- X-ray alignment to profile monitor (YAG screen) - to ensure beam, center and position if needed (undulator move if vertical adjustment is needed)
- Transport beam to end of XRT, adjust alignment in X and Y direction if needed
- To target chamber and imaging system for precision alignment if needed
- TCC evaluation as a function of the experiment
- Note: 2-6h of MD time requested if there has been no beam for some time (3-4 weeks). Additional 2h required at beginning of experiment for standard (long pulse) experiments. Constant evaluation required for non-LP experiments.
|