- Instructions from Kaz:- Mount the detector using a black adapter plate. Detector connected to the adapterplate using only 2 screws (not all 4). (In fact, do we even need the adapter plate?) Done.- Prepare water chiller- Disconnect water chiller from network (if it's connected). Done.- Prime the water chiller using the short hose (in the FAR hall detector cabinetlock key is 0624). Run the pump at 100%, 50%, and 10%, 10minutes at each setting. (Done)15% = 2.8 l/m50% = 3.4 l/m100% = 4.4 l/m- Reconnect water chiller to network.- connect water chiller to detector, and start running. Flow should be ~2.4LPM.- epix10k2m power- attach power cables to PDU...label cables if necessary. Do not attach toepix10k2m yet.- pin-out the epix10k2m power cables.
Quad0 A-M 1V B-N 1V C-P 1V D-R 0V E-S 1.5V F-G 0V U-V 10V Quad1
A-M 2V B-N 2V C-P 2V D-R 0V E-S 2.5V F-G 0V U-V 20V Quad2
A-M 3V B-N 3V C-P 3V D-R 0V E-S 3.5V F-G 0V U-V 30V Quad3 A-M 4V B-N 4V C-P 4V D-R 0V E-S 4.5V F-G 0V U-V 40 - if pin-out is ok, turn off power, and connect cables to detector.- If water is flowing, turn on power.
- Instructions from Kaz:
- Detector bolted to stand just out of x-ray beam per Chollet instruction. To be positioned later.
- Cables between MPOD and PDU connected.
- 15 ft. ePix Quad cables labelled and connected.
- Chiller loop short-circuited, run @18C and 15% power for ~10 min.