ATTENDEES
TOPICS:
Need to know-
1) the scope of the installation effort for each subsystem.
2) How much can be done without beam, before April turn-on
Current Plan for April Start-up
- April 1st - begin 2 weeks of PPS
- April 19th - beam on
- April 19 through May 5 - beam tune-up
- May 6 - Users start
Possible Alternate Plan
- April 19th through September no 120Hz user experiments
- April 19th through September User experiments at 30Hz
- April 19th through September testing at 120Hz through TD11 only
Switches to be upgraded
swh-in20-nw02 (bp01, bp02, rf01)
swh-li21-nw01 (bp01, bp02, bl01)
swh-li24-nw01 (bp01, bp02, rf01, bl01)
swh-b136-nw01 (bsy0-bp01)
swh-b106-nw01 (bsy0-bp02)
swh-b105-nw01 (ltu0-bpo1, ltu1-bp01)
swh-b911-nw01 (ltu1-bp02, ltu1-mg01?)
swh-b912-nw01 (ltu1-bp03, ltu1-mg02?)
swh-b913-nw01 (ltu1-bp04,und1-bp01,bp02)
swh-b921-nw01 (und1-bp03,bp04,dmp1-bp01