ATTENDEES

TOPICS:

Need to know-

1)      the scope of the installation effort for each subsystem.

2)      How much can be done without beam, before April turn-on

Current Plan for April Start-up

  • April 1st - begin 2 weeks of PPS
  • April 19th - beam on
  • April 19 through May 5 - beam tune-up
  • May 6 - Users start

Possible Alternate Plan

  • April 19th through September(question) no 120Hz user experiments
  • April 19th through September User experiments at 30Hz
  • April 19th through September testing at 120Hz through TD11 only

Switches to be upgraded

swh-in20-nw02         (bp01, bp02, rf01)
swh-li21-nw01(question)     (bp01, bp02, bl01)
swh-li24-nw01          (bp01, bp02, rf01, bl01)
swh-b136-nw01        (bsy0-bp01)
swh-b106-nw01        (bsy0-bp02)
swh-b105-nw01        (ltu0-bpo1, ltu1-bp01)
swh-b911-nw01        (ltu1-bp02, ltu1-mg01?)
swh-b912-nw01        (ltu1-bp03, ltu1-mg02?)
swh-b913-nw01        (ltu1-bp04,und1-bp01,bp02)
swh-b921-nw01        (und1-bp03,bp04,dmp1-bp01