Attendance:
Presentation:
Agenda/Notes:
- ePixM:
- Beamtime prep, Status:
- Burn test at -85V (Xavier)
- passed the burn test
- Getting the detector running in DAQ; (Alex)
- Take some copper fluorescence data (Zongde)
- Setup insatllation at MFX beam dump table, And check the fibers connection to the server;
- Date: 26th Aug(Monday)?
- Moving forward to the beam table: Wed (28th) or Thur (29th) if possible
- Physical setup to secure the camera;
- Will discuss with Chris Koerber
- Checking we have the multitosingle mode converter box;
- Testing the timing scan and trigger rate setting script;
- Timing scan tested.
- Intensity scan should be same as before.
- Setting up the pre-setup meeting (include TID);
- Beamtime week
- Get the measurement plan
- The week before the beamtime;
- Schedule the staffing;
- Ensure we have the needed support;
- Burn test at -85V (Xavier)
- Beamtime prep, Status: