Attendance:
Presentations:
Agenda/Notes:
- ePixM:
- Beamtime prep, Status off:
- Getting the detector running in DAQ;
- Getting the fibers installed at MFX and to server;
- Physical setup to secure the camera;
- Checking we have the multitosingle mode converter box;
- Cables and supplies to run the camera and what bias we need to apply
- Light shield to block visible light;
- Evaluate the data coming out of the detector;
- Testing the data analysis scripts and visualisations;
- Testing the timing scan and trigger rate setting script;
- Setting up the pre-setup meeting (include TID);
- Get the measurement list together;
- Schedule the staffing;
- Ensure we have the needed support;
- AMI-2
- Beamtime prep, Status off: