Attendees: Walter Wittmer Selina Green Rossignol, Charles F Tom Spinka Yang, Steven Jing Yin Mitchell Cabral Alex Wallace Nate Landis Ginger DeContreras Concepcion, Traci Edward Paul Chin Hardin, Corey L. Robert Plummer, Velynda Bertomen
Technical Path to DR and OPA Reviews
Topics | Notes |
---|
Worry List | Action Items: - All SMs and Owner of the item from the worry list will need to review, update and follow up as needed.
|
DR Preparation | DR Template - What are the 5-6 high level steps that are needed to get you to CD-2/3? P6 tasks too detailed
- Cost and Schedule Dashboard - Traci will provide
- Annotate and use red banner to give high level message
- Cost comparison - Traci will provide
- Explain changes. "TBD" area will be corrected by Traci.
- One-pager
- If System is on critical path, presenter should address
- CD-3A Long Lead Procurements have been identified (HE-LP). Remainder of procurements are after CD-2/3.
- Risk table - Karl Flick will provide. Additional Monte Carlo slides will be provided by Charles.
- New Challenges Resulting from Notional Funding Profile
- Include Deliverability Issues as a direct result of flat funding profile
- Include mitigation issues to address each issue
- Items Yet to be Addressed
- Recommendations from Prior Reviews
- Laser folks to meet offline to discuss how to present
- Show the examples most pertinent to charge questions
|
Next TI meeting | |