An attempt at capturing the remaining work to (approximately) complete the transition of Fermi software as we approach the end of the original 10-yr mission goal.
Code Development
Item | Description | Who | Deadline | Status | JIRA |
---|---|---|---|---|---|
Build Products Production
Item | Description | Who | Deadline | Status | JIRA |
---|---|---|---|---|---|
Expose externals via https | |||||
Docker | |||||
conda | Alex | IN PROGRESS | |||
Mac OS Support
Item | Description | Who | Deadline | Status | JIRA |
---|---|---|---|---|---|
set up lease of servers | NOT STARTED | ||||
Using Containers in L1 and Simulations
Item | Description | Who | Deadline | Status | JIRA |
---|---|---|---|---|---|
Operating L1 etc
Item | Description | Who | Deadline | Status | JIRA |
---|---|---|---|---|---|
cleanup documentation | TomS, Warren | IN PROGRESS | LONE-206 | ||
L1 GR branch builds | Heather | IN PROGRESS | |||