You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

Agenda - Minutes (here\)

Details for the Web&Audio connection with ReadyTalk (here)

  1. Consolidation of the Beamline Schedule (Marco, Ken, Stepan)
    1. The current baseline considers the HPS experiment installed inside the alcove downstream the CLAS12 experiment in Hall-B. This decision was taken after consultation with the JLAB management, but after the submission of the proposal in May'13. An addendum to the proposal (here) and an implementation plan (here) were developed to describe the feasibility as well as the impact on the schedule of both experiments. The old schedule as described in the proposal and presented at the DOE Review in July'13 is available V500 (here ). The preliminary closeout report (here)  has many comments along the line of the consolidation of the schedule for the installation of HPS in the alcove, in particularly of the beamline and its explicit integration with the JLAB 12GeV upgrade. The most important comments are summarized in this table at the end of this page (here).  We are required to consolidate of the baseline schedule for the beamline  especially  to monitor the real impact of the tasks toward the HPS installation in September'14, as well as the commissioning in October'14. A draft schedule of the full experiment available V600 (here) and an extract of the beamline only is available here.  
    2. Plan and Elevation drawings of the Beamline baseline layout. (here)
    3. Ken's slides (here
    4. Addendum to the proposal (here\)
    5. Implementation plan (here\)


  2. SVT&DAQ review preparation (Tim, Ryan, Marco)
    1. The Review will be held on Thusday November 5. The Charge for the review has been finalized (here). The key points to be reviewed are the technical status of the project and the schedule toward the installation in Septenber'14. The review panel will be composed by Marco (chair), John, Stepan and four external reviewers. Tim and Ryan as Project Leaders of the SVT and SVT DAQ project respectivly will act as link persons in charge to prepare the agenda and make the documentation available to the reviewers few days in advance. A draft list of talks is expected by Oct.29 while the relevant documentations and the final talks by  Nov.1.
    1. Review Panel (final) :

 

 

 

Marco Oriunno

SLAC

Chair

John Jaros

SLAC

Co-Chair

Stepan Stepanian

JLAB

Co-Chair

Tim Nelson

SLAC

Link person to the SVT project



External Reviewer



External Reviewer

 

 

External Reviewer

 

 

External Reviewer


  1. FY13 Budget endgame (Marco)
    1. With the FY13 closing, it's a good opportunity to review the cost incurred and discuss if the spending projection for FY14 are still good.

  2. Around the table, AOB (All)

  • No labels