This is the place where Detector Ops group will keep the most up to date schedule that they have for when detectors prototypes will be delivered to the ASC for integration into the DAQ and initial testing. Currently this contain the timeline for the ePixHR (5kHz), ePixM (5kHz), and the ePixUHR (33kHz) cameras . Additionally this page will also contain expected delivery dates for production detectors (spares of existing detector types), delivery dates for detectors that is out for refurb, key delivery dates for testing capability, and scheduled beam times.
Prototype Delivery
ePixHR (5 kHz) camera
For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.
Camera | type | Aim | Date at ASC | Previous delivery date | Comments |
|
|
|
| ||
|
|
|
| ||
|
|
|
| ||
ePixHR5kHz Quad | boards only | Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ). | August 2023 | May 2023; end March 2023.; Feb 2023;December 2022 | This delivery time is for boards only. |
ePixHR5kHz small prototype | ASIC V4. | Small prototype camera for first testing of ASIC v4. | August 2023 (camera with sensors) | July 2023 (just ASIC, check with kenney about sensor version), June 2023 (pending ASIC submission) | |
ePixHR5kHz full Camera | ASIC v4. | Initial testing of full camera and in lab calibrations. | End of November 2023 |
ePixM camera (5 kHz)
A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023. 3 Cameras will be delivered.
Camera | type | Aim | Date at ASC | Previous delivery date |
ePixM5kHz | Not back thinned | Integration into DAQ; Initial ASC performance testing. | End of August | July; Mid May; end March 2023; Feb 2023 |
ePixM5kHz | Back thinned | Initial testing of the ePixM camera at ASC and in lab calibrations. | December 2023 | September 2023; March 2023 |
ePixUHR (33 kHz)
For the UHR camera, the use of a hardware emulator will allow for start of DAQ integration. The first prototype detector will be delivered in April 2023. Commissioning of science cameras will happen in the 2026-2027 time frame.
Camera | type | Aim | Date at ASC | Previous delivery date |
|
|
|
| |
ePixUHR33kHz | Integration into DAQ and initial testing. | April 2023 |
Production Camera Delivery
Camera | type | Aim | Date at ASC | Previous delivery date | Need date in hutch |
ePix10k small, 1mm Si | sidefacer | Added to operations; Commissioned by Sebastien. | delivered. | July 2022 | N/A |
ePix10k2M.2 | non-ghosting ASICs | Added to operation; currently aimed at MFX but needs to be discussed with beamlines ones it is delivered. | May 2023 | April 2023; Nov. 2022 | ASAP |
ePixM5kHz | 90 | To be installed at REXS chamber at qRIXS | April 2023 | ||
ePixM5kHz | 0 | To be installed at ChemRixs chamber | April 2023 | ||
ePixM5kHz | ? | To be installed at the end of new (currently not excisting) spectrometer arm next to qRIXS spectrometer arm | At least a year after first ePixM detector | ||
ePixHR5kHz 2M | Large ePixHR5kHz camera | To be installed at TXI. | After start 2024 (chamber delivered start 2024) | ||
ePixHR5kHz small | Small ePixHR5kHz camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. | ||
ePixHR5kHz small | Small ePixHR5kHz camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. | ||
RIXSccd | CCD | System 1, at STA for shimming down the sides and the bolts. | Mid August | July 2023 | October 2023 |
RIXSccd | CCD | System 2, at STA for shimming down the sides and the bolts. | Sept. 2023 (3 weeks after system 1) | August 2023 | TBD |
Refurb. Delivery
Camera | type | Aim | Date at ASC | Previous delivery date | Need date in hutch |
|
|
|
Delivered ASC 2/23/2023 |
Testing capability schedule
Capability | Type | Aim | Date available | Previous availability date |
Running LCLS-II detectors at XPP. | LCLS beam line testing | Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there | Available | N/A |
Running LCLS-II detectors at MFX. | LCLS beam line testing | Run fiber from RIXS to MFX so LCLS-II detectors (ePixM, ePixHR) can be tested there | Available | N/A |
Running LCLS-II detectors at FEH. | LCLS beam line testing | Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI | Available | N/A |
E-gun X-ray source | ASC X-ray source | pulsed X-ray source at ASC | TBD | |
Running ePixM at MFX (Frankenstein) | LCLS beam line testing | install sufficient number of fibers to MFX to run the ePixM camera | January | N/A |
Beamtime schedule
Experiment number | Station | Aim | Dates | Lead from Ops team side |
X-10025 | MEC | Energy and burst rate frontier using a GaAs Icarus Detector. | 2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day) | Philip Hart |
| ||||
| ||||
| ||||
| ||||
| ||||
| ||||
RUN 22 (Jan 8 - July 3, 2024) | ||||
TBD | MFX | TBD | Feb 11+12, day | Conny Hansson |
TBD | MFX | TBD | 17-Mar, day | Conny Hansson |
TBD | MFX | TBD | 21-Apr, day | Conny Hansson |
TBD | MFX | TBD | 15-May, night | Conny Hansson |
Potential parasitic time at MFX | ||||
TBD | MFX | TBD | 15-17 April, night | |
TBD | MFX | TBD | 18-19 April, night | |
TBD | MFX | TBD | 22-Apr, night | |
TBD | MFX | TBD | 10-14 May, day | |
TBD | MFX | TBD | 13-14 May, night | |
TBD | MFX | TBD | 13-15 June, night |