Date
Attendees
Goals
- Set and status planning activities for detector development and deployment.
Discussion items
Time | Item | Who | Notes |
---|
20 min | Deployment 3-wk plan | Team | Shift coverage this week. - F 0730: X407 (Sun), JF, ePix, status?
- F 0730: P172 (Fromme) JF4M (on-call)
- F 2100 - 0300: Jungfrau/CSPAD@CXI: Kaz/Mark
|
10 min | Other beamtime-related | | - Wave8 testing/status?
- ePix10k Constants status/plan? Meet w/TID Thursday to discuss. (Pedestals w/bragg, AML v FL, ?)
- Baseline JF and 2M 'traveller' pages on Confluence.
- Collect and analyze any remaining in-lab test data.
- Next detector deployed: Kayla to lead meeting for mapping detectors to experiments
|
30 min | Priorities | All | - Group priorities review:
- Testing
- Setup ePix10k, ePix100, JF smalls for test in lab (~there)
- Understand charge injection issues.
- Baseline tests on smalls pre-deployment.
- Parametric performance tests (10k first)
- Analysis
- Gather and process relevant commissioning data for Mp travellers on Confluence.
- Solid pedestals
- Noise map
- Response uniformity (mini-X cu-fluorescencce)
- Bootstrap gain (sealed source)
- Linearity (signal injection)
- Documentation
- Complete on-line travellers for Mp detectors
- Development
- RIXS-CCD, review draft Project Plan w/NEH 2.2
- RIXS-CCD Concept Design (R to set meeting to talk cooling options)
- Anton project at UCB/SSL (milestone/schedule revision received)
- SXR Downselect prep
- Lab 'commissioning'
- DAQ
- Storage nodes
- LCLS I/II compatibility
- Table seismic
- Laser table re-cert
- BIO for racks in chase
- DP node purchase
- Sealed source purchase (M&S evaporating)
Actions:
|
30 min | Status | | CH: (Are we ready tot fix dashed line issue in the hutches?) - Charge injection scripts on 10k smalls for mask tests.
RA: (Are we on trac for Lin tests, and when to schedule him?) - Loan stages to CXI....ensure return.
- Meet re cooling concepts...met with Jim re outside space: not much.
KP: JSA summary list circulated - XPP/MFX/XCS fibers due this week, other wise need ugly solution.
- Small Rayonix testing can be done by others.
- XPP/XCS power cable pinout (controls needs to tell us MPOD working)
PH: |
5 min | Budget Update | mmck | - M&S Status (Through July)
- Labor snapshot (June actuals):
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule. |
10 min | Any other business | | |
Action items