Date

Attendees

Goals

  • Set and status planning activities for detector development and deployment.

Discussion items

TimeItemWhoNotes
30 minStatusAll

Single 90 min meeting going forward, rather than two 60min meetings?

ePix Update:

    • Green-liht to TID for following:
      • $60k for parallel ePix10k flipchip bonding run (FY19)
      • $75k to build two new ePix100 detectors (one front-looking, one side-looking), repair the existing compromised units, and store the spare modules against future needs.  Please allocate half of this against 16152-A4001 ePix Support, and the other half against 16158-A4001 Other Detector Support.
      • $5k for an identical copy of the new ePix10k shroud, so that the two 2M cameras will be physically identical.  Please use PA code 16152-A4001 ePix Support for this M&S.
      • $1k for a pair of cases with custom foam for the ePixBig cameras.  Please use PA code 16152-A4001 ePix Support for this M&S.
    • Still to consider:
      • $3k for metrology of existing ePixBig (FY19)
      • $25k to formally release ePixBig drawings/models in TeamCenter (FY20)

    • Testing has begun on ePixHR: Chip is alive and registers can be programmed...more results soon. Rebaseline after we know whether it works.
  • SXR requirements doc signed off.
  • TES re-baseline document not yet forwarded to LCLS mgmt. I'm late on this.
  • Project document for MCP/TImepix is in review with UCB finance. Need to get funding rolling, and to set up a visit to kick this off.
  • Costed proposal from UCB received....lots of spending in FY 19 that will be hard to accomplish.
  • Are we missing some 10k Smalls?
  • Need to conclude the fiber saga.....collect items from Ernesto and TID (timing crate)?
  • Status of 'buy' list?

 

 

Status:

  • RA: Added to 'buy' list....need new base plate ($4k??), stages,
    BIO is in review...
    JF mech design underway
    Wavefront sensor work with Matt Seaburg.
    JF interface document development....where do we want to draw the line? MEC EMP testing CSPAD/ePix Date TBD
  • PH: EMP testing confusing, but 10k didn't fall over.
    CSPAD Quad given to TID for isolation/testing as next stage.
    Marc Foster: no obvious solution for fibers.
    ePix10k and ePix100 setup on XCS for software development.
    Paper published in SPIE conference proceedings.
    CSPAD going on eBay....better use??
  • KN: Wave8 for FIM CDR 5/30.
    Much NEH crap transport.
    Laser setup this week.
  • KZ: Working RIXS CCD procedure.
    ePix10k requires new MPODS, working issue
  • Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
  • eGun interlock doc (2wk.)
  • Status documentation/procedures effort
  • How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 minBudget Updatemmck
  • ASC: $268k cost + committs, $14k is in error and will be removed. Asking PA account be closed.
  • Detector I&D (16159): $169k costs + commits ($401k budget)
      • M&S $69k costs + commits ($142k budget)
      • Labor:$40k ($80k budget)
      • Shop:$14k ($66k budget)
  • Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 minReview ASC First Projectsall

Coordinate/update lab schedule.

10 minAny other business  

Action items

  • Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster  