Set and status planning activities for detector development and deployment.
Discussion items
Time
Item
Who
Notes
30 min
Status
All
ePix Update:
- Carrier PCB board required for testing the HR ASIC has been completed and is now in fab.
- PCB will be back next week and we will bond the chips
- Testing will start the week after
- Mechanical housing of the HR camera (140k equivalent) will be complete in the next week and a half.
ePixM
- Layout of ePixM LFoundry complete (3 variants full size)
- Layout of test structures almost complete
- Fabrication should start around the end of next week
Phase III was approved at PEC on Friday, re-planned to deliver working prototype for downselect vs. VFCCD in late 2020.
1 in-air ePixBig (Jan 2020) and 4 thick-Si MEC (May 2020) quads also approved. Need a kickoff meeting and probably a little more hands-on than first article(?)
Peter Denes visiting tomorrow to discuss SXR imager requirements:
50um pixel pitch
15e- rms read noise
5kHz frame rate or greater
512x512-class pixel format, to be tileable to 1Mp-class with >90% fill factor. Buildup from smaller 4-side buttable modules is acceptable.
1000 photon well capacity @1.5keV530eV
>90%70% QE at 277-1.5keV
High Vacuum compatible (10e-9T)
Compatible with 2m electronics cabling and cooling hoses to allow in-chamber articulation.
Compact packaging for mounting within q-RIXS vacuum chamber (dimensions to be specified, but like iVFCCD concept))
Visible-blind to laser pump background.
Decide ASC electrical after move-in costs known
Rebar scan complete, anchors set(?)....set up ASC coordination meeting (KZ)?
Status JF 4M effort. 4pm meeting today....
Update > Status RIXS-CCD test planning
Masks not here yet, checking with Sallie.
Ground issues resolved from first test?
Late March slips to mid-April??
Do first test at SSRL to decouple from ASC sked??
MEC EMP testing CSPAD/ePix Date TBD
PH gone first week April
KN Wave8 upgrade for FIM CDR Mid-April
ePix10k requires new MPODS, working issue
Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
eGun interlock doc (2wk.)
Lost cabinets were not delivered....(2wks)
KZ: Control room furniture install this afternoon.
Vacuum equipment moving today w/techs.
Riggers set for Thursday 10am.
Status documentation/procedures effort
How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
5 min
Budget Update
mmck
ASC: $191k spent, $62k remains
Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
15 min
Review ASC First Projects
all
Coordinate/update lab schedule
10 min
Any other business
Action items
Philip Hart to determine the necessary fiber count to B84 in consult with Mark Foster