Wednesday, Aug-26-2009 Software DayProgram Deputy: Rick Iverson Physicist Contact: Rick Iverson(day/owl shift) Controls Deputy: Mike Zelazny Magnet Controls Contact: Kristi Luchini References Day Shift | ...6:00am | 8:00 | 9:00am | 12:00pm | 1:00 | 4:00 | 5:00 | LI26 Pwr Off | LI25 Pwr Off | LI26 Pwr Off | LI26 Pwr Off | LI26 Pwr Off | LI26 Pwr On | Beam Off | Beam Off | Beam Off | Beam Off | Beam Off | Beam Off | Turn Beam On | | Network Install | Network Install | Network LI25 | Network LI24 |
[ Schedule | LCLS Commissioning Software Day ] | Item | Start Time | Duration | Comment | Status | Person | Subsystem | Description | | 6:00am | Beam Off | 1 | 8:30 | 2hr | | | K. Luchini | Magnets | Release Magnet Software (prep) for li24-li25 | 2 | | 30min | | | E. Grunhaus | Orcle Db | Update Oracle db with li24-li25 magnet changes | 3 | | 30min | | | A. McCollough | PEM | Install MCOR-to-VME cables in KA24-01, KA25-01 | 4 | 9:00 | 15min | | | E. Grunhaus | Aida | Update Aida Name Server | 5 | 9:15 | 15min | | | E. Grunhaus | SCORE | Update SCORE Name Translation | 6 | 10:00 | 2hr | | | J. Rock | Oracle & System | Update Oracle Passwords | 7 | | 20min | | | | Alarms & ALH | Update alarms with li24-li25 epics names and ALH with new iocs | 8 | 10:30 | 1hr | | | K. Luchini | Magnets | Reboot in20,li21-23,li26-bsy,ltu,und,dmp magnet iocs | 9 | 11:00 | 1hr | | | P. Natampalli | SCORE | SCORE Release to coordinate with Oracle Password Upgrade | 10 | 11:30 | 5min | | | K. Luchini | IOC Manager | Release IOCMagager to add new magnet iocs. | 11 | 12:00pm | 2hrs | | | K. Luchini | Magnets | Checkout Network in li24-li25. Reboot li24, li25 magnet iocs. | 12 | 1:00 | 1hr | | | H.Loos | Matlab | Update matlab programs with proper epics name for coorector magnets. | 13 | 2:00 | 20min | | | P.Natampalli | SCORE | Test by loading magnet LI24/LI25 config | 14 | | 1hr | | | J. Rock | IRMIS | Run Irmis script to update IRMIS db for BSA/Orbit display | 15 | | 10min | | | P. Chu | Model | Model Update XAL for LEM/Model | | 4:00pm | Search Time & LI26 Pwr On | | 5:00pm | Turn Beam On - Program Starts |
*Note:*Feedback testing will take place during Thursday MD w/D. Fairley. Subsystem | Contact | Description | Magnets | K. Luchini | Release Magnet Software | | A. McCollough | Install MCOR-to-VME Cables in KA24-0145 and KA25-0145 | Oracle Db | E. Graunhaus | Update Oracle Db | Aida | E. Graunhaus | Rebuild Aida Name Server | SCORE | E. Graunhaus | Rebuild SCORE Name Traslator (Set Catagory) | SCORE | P. Natampalli | Release SCORE changs related to Oracle Password Upgrade | Archiver | B. Hall | Update Archiver with LI24-25 magnet correctors | Alarms | J. Rock | | Update Alarm ioc with Magnet corrrector STATSUMY instead of STRG | IRMIS: | J. Rock | Run IRMIS script to update db used by BSA and Orbit display | Network | T. Lahey | Install network for li24 and li25 magnet ioc, crate and ts | Matlab | H.Loos | Update Matlab programs with the proper EPICS name for li24/li25 correctors. | IOC Manager | K.Luchini/S.Hoobler | Release IOCManager db with new magnet iocs. | Model | P. Chu | Update XAL for LEM/Model |
|