Wednesday, Aug-26-2009 Software Day
Program Deputy: Rick Iverson
Physicist Contact: Rick Iverson(day/owl shift)
Controls Deputy: Mike Zelazny
Magnet Controls Contact: Kristi Luchini
References
Day Shift |
...6:00am |
8:00 |
9:00am |
12:00pm |
1:00 |
4:00 |
5:00 |
LI26 Pwr Off |
LI25 Pwr Off |
LI26 Pwr Off |
LI26 Pwr Off |
LI26 Pwr Off |
LI26 Pwr On |
Beam Off |
Beam Off |
Beam Off |
Beam Off |
Beam Off |
Beam Off |
Turn Beam On |
|
Network Install |
Network Install |
Network LI25 |
Network LI24 |
[ Schedule |
LCLS Commissioning Software Day ] |
Item |
Start Time |
Duration |
Comment |
Status |
Person |
Subsystem |
Description |
|
6:00am |
Beam Off |
1 |
8:30 |
2hr |
|
|
K. Luchini |
Magnets |
Release Magnet Software (prep) for li24-li25 |
2 |
|
30min |
|
|
E. Grunhaus |
Orcle Db |
Update Oracle db with li24-li25 magnet changes |
3 |
|
30min |
|
|
A. McCollough |
PEM |
Install MCOR-to-VME cables in KA24-01, KA25-01 |
4 |
9:00 |
15min |
|
|
E. Grunhaus |
Aida |
Update Aida Name Server |
5 |
9:15 |
15min |
|
|
E. Grunhaus |
SCORE |
Update SCORE Name Translation |
6 |
10:00 |
2hr |
|
|
J. Rock |
Oracle & System |
Update Oracle Passwords |
7 |
|
20min |
|
|
|
Alarms & ALH |
Update alarms with li24-li25 epics names and ALH with new iocs |
8 |
10:30 |
1hr |
|
|
K. Luchini |
Magnets |
Reboot in20,li21-23,li26-bsy,ltu,und,dmp magnet iocs |
9 |
11:00 |
1hr |
|
|
P. Natampalli |
SCORE |
SCORE Release to coordinate with Oracle Password Upgrade |
10 |
11:30 |
5min |
|
|
K. Luchini |
IOC Manager |
Release IOCMagager to add new magnet iocs. |
11 |
12:00pm |
2hrs |
|
|
K. Luchini |
Magnets |
Checkout Network in li24-li25. Reboot li24, li25 magnet iocs. |
12 |
1:00 |
1hr |
|
|
H.Loos |
Matlab |
Update matlab programs with proper epics name for coorector magnets. |
13 |
2:00 |
20min |
|
|
P.Natampalli |
SCORE |
Test by loading magnet LI24/LI25 config |
14 |
|
1hr |
|
|
J. Rock |
IRMIS |
Run Irmis script to update IRMIS db for BSA/Orbit display |
15 |
|
10min |
|
|
P. Chu |
Model |
Model Update XAL for LEM/Model |
|
4:00pm |
Search Time & LI26 Pwr On |
|
5:00pm |
Turn Beam On - Program Starts |
*Note:*Feedback testing will take place during Thursday MD w/D. Fairley.
Subsystem |
Contact |
Description |
Magnets |
K. Luchini |
Release Magnet Software |
|
A. McCollough |
Install MCOR-to-VME Cables in KA24-0145 and KA25-0145 |
Oracle Db |
E. Graunhaus |
Update Oracle Db |
Aida |
E. Graunhaus |
Rebuild Aida Name Server |
SCORE |
E. Graunhaus |
Rebuild SCORE Name Traslator (Set Catagory) |
SCORE |
P. Natampalli |
Release SCORE changs related to Oracle Password Upgrade |
Archiver |
B. Hall |
Update Archiver with LI24-25 magnet correctors |
Alarms |
J. Rock |
|
Update Alarm ioc with Magnet corrrector STATSUMY instead of STRG |
IRMIS: |
J. Rock |
Run IRMIS script to update db used by BSA and Orbit display |
Network |
T. Lahey |
Install network for li24 and li25 magnet ioc, crate and ts |
Matlab |
H.Loos |
Update Matlab programs with the proper EPICS name for li24/li25 correctors. |
IOC Manager |
K.Luchini/S.Hoobler |
Release IOCManager db with new magnet iocs. |
Model |
P. Chu |
Update XAL for LEM/Model |