Driver and Device Support

Start Date: 01-Mar-06

Bus Type*: *VME

Module

I/O Type

Num Of Weeks

Date Needed

Status

Assigned To

Acromag IP-440

DI

1-hour

20-Mar-06

done

S. Allison

Acromag IP-445

DO

1-hour

20-Mar-06

done

S. Allison

Acromag AVME9670

IP Carrier

1-hour

20-Mar-06

done

S. Allison

Acromag IP-231

DAC

2-day

20-Mar-06

in progress

K. Luchini

Hytec IP-8402

DAC

2-days

20-Mar-06

in progress

K. Luchini

Hytec IP-8413

ADC

2-days

15-Jul-06

Not Avail

K. Luchini

BiRa VSAM 7305

Scanning ADC

2-day

20-Mar-06

done

K. Luchini

Record Support

Start Date: 01-Mar-06

Type

Num Of Weeks

Date Needed

Status

Assigned To

VME Card

1-hour

20-Mar-06

done

K. Luchini

EDM Display Mockups

Start Date: 01-Mar-06

Description

Num of Weeks

Date Needed

Status

Assigned To

Single Unit

2-days

17-Mar-06

in progress

K. Luchini

Module Diag

2-days

17-Mar-06

in progress

K. Luchini

XCOR Units

2-days

17-Mar-06

done

D. Rogind

All Units

2-days

17-Mar-06

in process

D. Rogind

Standardize

2-days

17-Mar-06

done

D. Rogind

Summary Status

2-days

02-Apr-06

TBD

TBA

Diagnostic

2-days

02-Apr-06

TBD

TBA

Calibratin Diag

2-days

01-Jul-06

TBD

TBA

History Plot

2-days

01-Jul-06

TBD

TBA

Correlation Plot

2-days

01-Jul-06

TBD

TBA

Strip Charts

2-days

01-Jul-06

TBD

TBA

EDM Displays

Start Date: 01-Mar-06

Description

Num of Weeks

Date Needed

Status

Assigned To

SCP Panels

Start Date: 01-Jul-05

Num of Weeks: 1

Description

Micro

New/Existing

Filename

Date Needed

Status

Assigned To

Dev Micro Units

XL01

N

MGNTXL01.PNL

10-Sep-05

done

J. Paz

Dev Micro Units

XL02

N

MGNTXL02.PNL

10-Sep-05

done

J. Paz

Dev XL03 Units

XL03

N

MGNTXL03.PNL

10-Sep-05

done

J. Paz

Dev XL04 Units

XL04

N

MGNTXL04.PNL

10-Sep-05

done

J. Paz

Dev XL05 Unitx

XL05

N

MGNTXL05.PNL

10-sep-05

done

J. Paz

Dev Template

XLXX

N

MGNTXLXX.PNL

10-Sep-05

done

J. Paz

Injector Units

IM20

N

MGNTIM20.PNL

03-Jan-06

done

J. Paz

Linac S21 Units

LM21

E

MGNTLM21.PNL

03-Jan-06

 

J. Paz

Linac S24 Units

LM24

E

MGNTLM24.PNL

03-Jan-06

 

J. Paz

Linac S25 Units

LM20

E

MGNTLM20.PNL

03-Jan-07

 

J. Paz

BSY Units

BM01

E

MGNTBM01.PNL

03-Jan-07

 

J. Paz

...