Capability

Type

Aim

Date available

Previous availability date

Running LCLS-II detectors at XPP.

LCLS beam line testing

Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there

Feb-March 2023

N/A

Running LCLS-II detectors at FEH.

LCLS beam line testing

Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI

June 2023 (subject to availability of installed fiber cable)

N/A
E-gun X-ray sourceASC X-ray sourcepulsed X-ray source at ASCTBD


Beamtime schedule

Experiment number

Station

Aim

Dates

Lead from Ops team side

X-10025

MECEnergy and burst rate frontier using a GaAs Icarus Detector.2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day)Philip Hart

DET

MFXEvaluate the checker mark problem on small ePix10k, and the issue with the 3 bad quads for the MFX 2m.2023: July 13 (Night), July 15 (Night)Conny Hansson

X-10051

MFXCalibration of small10k's after having corrected for the checker mark effect.2023: July 21 (Night)Conny Hansson

ePixHR

MFXEvaluate the performance of the ePixHR detector.2023: 29 Aug (night), 14+15 Sept. (night).Conny Hansson

ePixM

MFXEvaluate the performance of the ePixM detector.Early 2024Conny Hansson

ePixM

MFXEvaluate the performance of the ePixM detector.March-April 2024Conny Hansson

ePixM

chemRIXSEvaluate the performance of the ePixM detector.Before June 2024Conny Hansson

...