Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

ePix10k small, 1mm Si 

sidefacer

Added to operations; Commissioned by Sebastien.

Unclear

July 2022N/A

ePix10k2M.2

non-ghosting ASICs

Added to operation; currently aimed at MFX but needs to be discussed with beamlines ones it is delivered.

May 2023

April 2023; Nov. 2022ASAP
ePixM5kHz90To be installed at REXS chamber at qRIXS

April 2023
ePixM5kHz0To be installed at ChemRixs chamber

April 2023
ePixM5kHz?To be installed at the end of new (currently not excisting) spectrometer arm next to qRIXS spectrometer arm

At least a year after first ePixM detector
ePixHR5kHz 2MLarge ePixHR5kHz cameraTo be installed at TXI.

After start 2024 (chamber delivered start 2024)
ePixHR5kHz smallSmall ePixHR5kHz camera; same form factor as side facing ePix100To be installed at TXI.

end of 2023.
ePixHR5kHz smallSmall ePixHR5kHz camera; same form factor as side facing ePix100To be installed at TXI.

end of 2023.
RIXSccdCCDSystem 1, at STA for shimming down the sides and the bolts.Mid AugustJuly 2023October 2023
RIXSccdCCDSystem 2, at STA for shimming down the sides and the bolts.August Sept. 2023 (3 weeks after system 1)August 2023 TBD

Refurb. Delivery

Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

CSPAD 2M

CXI's large CSPAD detector

inner module is broken and need to be replaced. The Detector has been delivered to Kenney together with 2 small CSPAD units to be scavenged for the repair. To be returned for operation at CXI.

Dec 2022

Delivered ASC 2/23/2023

Feb 2023March 2023

...