Production Camera Delivery
Camera | type | Aim | Date at ASC | Previous delivery date | Need date in hutch |
ePix10k small, 1mm Si | sidefacer | Added to operations; Commissioned by Sebastien. | Unclear | July 2022 | N/A |
ePix10k2M.2 | non-ghosting ASICs | Added to operation; currently aimed at MFX but needs to be discussed with beam lines ones it is delivered. | April 2023 | Nov. 2022 | ASAP |
ePixM | 90 | To be installed at REXS chamber at qRIXS | April 2023 | ||
ePixM | 0 | To be installed at ChemRixs chamber | April 2023 | ||
ePixM | ? | To be installed at the end of new (currently not excisting) spectrometer arm next to qRIXS spectrometer arm | At least a year after first ePixM detector | ||
ePixHR 2M | Large ePixHR camera | To be installed at TXI. | After start 2024 (chamber delivered start 2024) | ||
ePixHR small | Small ePixHR camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. | ||
ePixHR small | Small ePixHR camera; same form factor as side facing ePix100 | To be installed at TXI. | end of 2023. |
Refurb. Delivery
Camera | type | Aim | Date at ASC | Previous delivery date | Need date in hutch |
CSPAD 2M | CXI's large CSPAD detector | inner module is broken and need to be replaced. The Detector has been delivered to Kenney together with 2 small CSPAD units to be scavenged for the repair. To be returned for operation at CXI. | Dec 2022 | Feb 2023 | March 2023 |
Testing capability schedule
Capability | Type | Aim | Date available | Previous availability date |
Running LCLS-II detectors at XPP. | LCLS beam line testing | Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there | Feb-March 2023 | N/A |
Running LCLS-II detectors at FEH. | LCLS beam line testing | Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI | June 2023 (subject to availability of installed fiber cable) | N/A |
E-gun X-rau source | ASC X-ray source | pulsed X-ray source at ASC | TBD |
Beam time schedule
Experiment number | Station | Aim | Dates | Lead from Ops team side |
X-10025 | MEC | Energy and burst rate frontier using a GaAs Icarus Detector. | 2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day) | Philip Hart |