This is the place where Detector Ops group will keep the most up to date schedule that they have for when detectors prototypes will be delivered to the ASC for integration into the DAQ and initial testing. Currently this contain the timeline for the ePixHR (5kHz), ePixM (5kHz), and the ePixUHR (33kHz) cameras . Additionally this page will also contain expected delivery dates for production detectors (spares of existing detector types), delivery dates for detectors that is out for refurb, key delivery dates for testing capability, and scheduled beam times.

Prototype Delivery

ePixHR (5 kHz) camera

For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.

...

A non thin entrance window detector will be delivered initially for DAQ integration purposes, followed by the cameras themselves, with thin entrance windows. Commissioning is set to start in April 2023. 3 Cameras will be delivered.

Camera

type

Aim

Date at ASC

Previous delivery date

ePixM5kHz

Not back thinned

Integration into DAQ

Feb 2023


ePixM5kHz

Back thinned

Initial testing of the ePixM camera at ASC and in lab calibrations.

March 2023



ePixUHR (33 kHz)

For the UHR camera, the use of a hardware emulator will allow for start of DAQ integration. The first prototype detector will be delivered in April 2023. Commissioning of science cameras will happen in the 2026-2027 time frame.

Camera

type

Aim

Date at ASC

Previous delivery date

ePixUHR33kHz

HW emulator

Integration into DAQ.

Jan 2023


ePixUHR33kHz


Integration into DAQ and initial testing.

April 2023


Production Camera Delivery

Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

ePix10k small, 1mm Si 

sidefacer

Added to operations; Commissioned by Sebastien.

Unclear

July 2022N/A

ePix10k2M.2

non-ghosting ASICs

Added to operation; currently aimed at MFX but needs to be discussed with beam lines ones it is delivered.

April 2023

Nov. 2022ASAP

Refurb. Delivery

Camera

type

Aim

Date at ASC

Previous delivery dateNeed date in hutch

CSPAD 2M

CXI's large CSPAD detector

inner module is broken and need to be replaced. The Detector has been delivered to Kenney together with 2 small CSPAD units to be scavenged for the repair. To be returned for operation at CXI.

Dec 2022

Feb 2023March 2023

Testing capability schedule

Capability

Type

Aim

Date available

Previous availability date

Running LCLS-II detectors at XPP.

LCLS beam line testing

Run fiber from RIXS to XPP so LCLS-II detectors (ePixM, ePixHR) can be tested there

Feb-March 2023

N/A

Running LCLS-II detectors at FEH.

LCLS beam line testing

Run fiber (DRP solution) from RIXS to FEH so LCLS-II detectors (ePixM, ePixHR) can be tested at MFX/XCS/CXI

June 2023 (subject to availability of installed fiber cable)

N/A

Beam time schedule

Experiment number

Station

Aim

Dates

Lead from Ops team side

X-10025

MECEnergy and burst rate frontier using a GaAs Icarus Detector.2023: 28 April (Night), 29 April (Day), April 30 (Night), May 1 (Day)Philip Hart