For the ePixHR camera a prototype small detector will be delivered, followed by a Quad, and finally the full camera. This is done in order to allow for the DAQ integration for the Quad (which is repeated 4 times for the full camera) to begin prior to delivery of the full camera and allow more time for this work. Commissioning is currently set for sometime in the end of 2023 (date to be confirmed), and one large camera and 2 small cameras will be delivered.
Camera | type | Aim | Date at ASC | Previous delivery date |
ePixHR5kHz | ASIC v2. | Integration into the LCLS-II DAQ and initial testing to feed into ASIC v3. submission. | April 2022 | |
ePixHR5kHz | ASIC v2. | Integration into the LCLS-II DAQ (new firmware structure) and initial testing. | October 2022 | |
ePixHR5kHz | ASIC v3. | Integration into DAQ and initial testing of ASIC. | November 2022 | |
ePixHR5kHz Quad | ASIC v3. | Integration into DAQ and software testing to allow for expansion to full camera (board integration for DAQ). | Feb 2023 | December 2022 |
ePixHR5kHz full Camera | ASIC v4. | Initial testing of full camera and in lab calibrations. | May 2023 |
...