Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Stave Loading Tooling in progress...

Summary of requirements for loading 19-1 Outer Barrel Stave:

  • Load RD53a Quad modules (drawing to be added) with connectors oriented as shown
  • Load modules onto 19-1 OB Stave (drawing to be added)
  • Load without collisions: 200 um nominal gap / 100 micron minimum gap between modules
  • ESD protection during loading: grounding of tooling
  • Mechanical protection of wire bonds during loading: stay clear area, handle using tooling only
  • Baseplate to be installed onto glue robot: weight limit 7kg (manual)

Summary of different requirements for loading 19-1 Inner Barrel Stave:

  • Load Triplet modules (drawing?)
  • Load onto 19-1 IB Stave (drawing?)

Design approach intended to avoid collisions during loading:

  • Closely toleranced pins/bushings
  • Same approach as for 19-0 Stave